Drain Story (2011)
Si vous désirez obtenir une traduction de cette décision
ou ordonnance, veuillez communiquer avec le bureau du Tribunal (voir
ci-dessous).
In the matter of the Drainage Act R.S.0. 1990, Chapter D.17, as
amended.
And in the matter of: Appeals to the Agriculture,
Food and Rural Affairs Appeal Tribunal by Kenneth & Lynda Anderson
of Blenheim; James & Ruth Anne Clark of Blenheim; Ross &
Joyce Brush, Blenheim; Jim Knowles, Blenheim; 657722 Ontario Inc.
(John McGuigan) of Cedar Springs; Ronald & Josephine Sullivan,
Blenheim; Ronald Patrick Sullivan & Clara Sullivan Life Interest,
Blenheim; David & Kathy Townsend, Blenheim; 1613339 Ontario
Inc. (Chris Stewart) under Subsection 48(1) and 54(1) of the Drainage
Act from the engineer's report and from a decision of the Court
of Revision on the Story Drain in the Municipality of Chatham-Kent.
Before:
Susan Whelan, Vice Chair (Chair of Panel); Kirk Walstedt, Chair;
Jack Young, Vice Chair;
Appearances:
Kenneth Anderson, appellant
John Kuntze, P.Eng., expert witness for the appellant, Mr. Anderson
Dennis H. Asher, counsel for Kenneth and Lynda Anderson
Ross Brush, appellant
George Girty, witness for the appellant upstream agricultural landowners
James P. Bourne, witness for the appellant upstream agricultural
landowners
657722 Ontario Inc. (John McGuigan) of Cedar Springs, appellant
and representative of upstream agricultural owners
Raymond Dobbin, P.Eng., expert witness for the appellant upstream
agricultural landowners
Janet McGuigan Kelly, counsel for the upstream agricultural appellants
Mr. Ed Dries, P. Eng., Engineer who prepared the Report and expert
witness for the Municipality of Chatham-Kent
Mr. Paul Courey, counsel for the Municipality of Chatham-Kent
Decision of the Tribunal
This hearing was held in the Council Chambers, Municipality of
Chatham-Kent (the Municipality"), in Chatham, Ontario on April
11, 12 and 13, 2011. Kenneth and Lynda Anderson; James and Ruth
Anne Clark; Ross and Joyce Brush; Jim Knowles; 657722 Ontario Inc.
(John McGuigan); Ronald and Josephine Sullivan; Ronald Patrick Sullivan
and Clara Sullivan Life Interest; David and Kathy Townsend; 1613339
Ontario Inc. (Chris Stewart) appealed to the Agriculture, Food and
Rural Affairs Appeal Tribunal (the "Tribunal') under Section
48(1) and 54(1) of the Drainage Act (the "Act") from the
Engineer's Report and from the decision of the Court of Revision
dated June 22, 2010 on the Story Drain.
The Engineer's Report titled "Story Drain" (the Report),
dated April 1, 2010, was prepared by Dillon Consulting Limited (the
"Engineer"). Mr. E.P. Dries, a professional engineer with
that firm, was designated under section 8(2) of the Act for overall
responsibility for the Report.
Elinor Mifflin, Clerk of the Municipality, performed the duties
of the Clerk of the Tribunal.
Prior to the beginning of the Hearing, the Tribunal issued an order
making all landowners assessed or compensated in the Report parties
to the hearing. The Clerk of the Municipality filed an Affidavit
of Service with the Tribunal as proof that all parties had been
served.
Preliminary Issue
Motion materials were filed by Mr. Asher approximately one week
in advance of the Hearing.
The Motion requested an Order from the Tribunal that the April
1, 2010 Engineer's Report had no status and the Tribunal lacked
jurisdiction to make a determination on the issues raised in the
appeals of the Municipality of Chatham-Kent Drainage Board (the
Drainage Board) decisions of May 11, 2010 and May 22, 2010 in the
absence of a report prepared in accordance with the legislation.
The basis of Mr. Asher's argument was that the Report was not prepared
in accordance with the requirements of section 78 of the Act as
stated by the Municipality.
Mr. Courey objected to the Notice of Motion. He argued it was not
a proper Motion as the factum contained no evidence, there was no
affidavit evidence, it was made late and it was returnable at the
Hearing. He concluded by stating the Motion clearly contained a
new ground of appeal that could have been dealt with long ago as
the Hearing had been delayed at the request of Mr. Asher's clients.
Findings on the Motion
The Tribunal noted that the Hearing was postponed in December 2010
at Mr. Asher's request in order to permit his clients more time
to prepare their case.
The four month time frame would have given Mr. Asher more than
adequate time to properly prepare and bring the Motion forward pursuant
to Rule 25 of the Tribunal's Rules of Procedure. This would have
allowed affidavits to have been filed by all parties.
Although the Tribunal's Rules of Procedure allow for a Motion to
be brought forward at a Hearing, the Tribunal did not hear the Appellant's
Motion prior to the start of the Hearing. Instead, arguments pertaining
to the grounds for the Motion were heard through the course of the
hearing. During those discussions, Mr. Courey objected to Mr. Asher's
line of questioning that the 2010 Report was not a valid report.
The Tribunal heard arguments from all parties during which Mr. Courey
raised the issue that the Tribunal did not have jurisdiction under
section 47 of the Act to deal with the validity of the Report. Mr.
Asher argued that the Tribunal had jurisdiction under section 51,
and also referred to the Tribunal's recent decision of Baer to support
his position.
The Tribunal Panel ruled that the Drainage Act is quite clear and
consistent. That section 47 (1) of the Act provides the right to
appeal to the referee if any owner of land is dissatisfied with
the report of the engineer on the grounds that it does not comply
with the requirements of the Act, and that an appeal of the report
on the grounds of non-compliance should have been made to the referee
within 40 days.
The Tribunal Panel also ruled that Section 51(1) does not give
the Tribunal the power to take the place of the referee in this
determination of non-compliance. It is clearly stated in section
51 that the Tribunal's powers are "where not so provided"
and the powers to determine non-compliance were clearly provided
in section 47 to the referee.
With respect to the Baer decision, the Panel advised that Tribunal
decisions are not normally precedent setting; and, in addition,
the Panel distinguished Baer from the case before them. The finding
by the Tribunal in Baer was that the Tribunal did not have an engineer's
report before them because it was an incomplete document; that is
not the case before this Tribunal Panel.
The Tribunal Panel continued the hearing on the finding of fact
that the 2010 Report was a valid report.
The Report Background
The Story Drain, which has been a project under the Drainage Act
for approximately 100 years, drains an agricultural watershed of
approximately 320 hectares in the geographic Township of Harwich
and outlets into a watercourse at the north limit of the former
Community of Erie Beach. From this point, the water flows through
the residential lots on the north and south sides of Towanda Blvd.
and then flows into Lake Erie.
The purpose of this drainage project is to incorporate and improve
the section of the watercourse through the residential properties
to provide a legal outlet for the Story Drain into Lake Erie.
In the mid 1980s, the portion of the open channel from the north
residential limit to the north limit of Towanda Blvd. was enclosed
with an 1800 mm diameter corrugated steel pipe. In 1994, the remainder
of the open channel from Towanda Blvd to Lake Erie was enclosed
with a 2000 mm corrugated steel pipe and a sheet pile outlet structure
was constructed at Lake Erie. All of this work was under the direction
of and funded by the Lower Thames Valley Conservation Authority
(LTVCA).
In 2005, an engineering report was prepared under Section 4 of
the Act that recommended improvement to the outlet structure and
the incorporation of the enclosed portion into the Story Drain.
This report was never adopted by the Municipality.
Over the years, typical improvements have been made on the residential
properties with regard to the alignment of the drain enclosure including
lawns and gardens and a garage that is constructed partially over
the drain enclosure.
The bottom of the corrugated steel pipe drain enclosure north of
Towanda Blvd. that was installed in the mid 1980's, is severely
corroded with extensive perforation and is considered as failed
and has resulted in loss of backfill at specific locations over
the pipe. The drain enclosure south of Towanda Blvd. appears structurally
sound and has an anticipated additional design life of approximately
15 years.
The Municipality proceeded under section 78 of the Act and the
2010 Report was prepared accordingly
The Issues
- .The issues before the Tribunal are as follows:
Should the engineering costs for the Story Drain 2005 report be
included in the 2010 Story Drain 2010 Report?
- Should the allowances for the right of way under section 29
of the Act be increased?
- Should an allowance for the existing pipe drain be included
under Section 31 of the Act?
- Should an alternate location for the Story Drain outlet through
the Erie Beach properties be investigated?
- Should Assessment Schedules A-1 and A-2 be amended?
- Should the assessment schedules for maintenance be amended?
- Should item 2 of Engineer's "Estimate of Cost" be
corrected to reflect the correct cost of the 48 m corrugated steel
pipe?
- Should the Court of Revision decision with respect to Roll #
10-610 (657722 Ontario Inc.) be allowed to stand?
- Should the appellants' legal and engineering costs form part
of the cost of this project?
Engineer's Outline and Assessment Rationale
Mr. Dries gave a brief outline of the project and his rationale
in assessing the cost of the project. He stated that a section of
enclosed drain north of Towanda Blvd. had failed and that the main
objectives of the Report were to replace that section of the drain,
and to incorporate the pipe section of drain in the Community of
Erie Beach into the Story Drain thereby providing for future maintenance
of this closed portion of the Story Drain.
He stated that allowances for right of way were provided in accordance
with section 29 of the Act to owners of the private lands through
which the enclosed drain must pass, and that this allowance was
based on a land value of $10,000 per acre. The Report also provided
an allowance in accordance with section 30 of the Act for damage
to adjoining property during construction.
He stated that the project was divided into two parts for the purpose
of determining the assessment distribution. Part 1 incorporates
the entire length of the existing private drain and provides a mechanism
for future maintenance and repair of that private drain. Part 2
provides for the reconstruction of the portion of the private drain
north of Towanda Blvd. Part 1 has a cost estimate of $19,640 and
Part 2 has a cost estimate of $32,660 for a total project cost estimate
of $52,300. The Engineer assigned approximately 75% of the engineering
and contingency costs of the entire works against Part 1, as this
value includes earlier costs related to the previous 2005 report
that was never adopted.
With respect to assessments, the Engineer explained the division
of costs for each of the two Parts. For Part 1, the drain incorporation,
the Benefit/Outlet Ratio (B/O Ratio) was approximately 36/64. (Benefit
$7,000 + Outlet $12,640 = $19,640). The benefit assessment was allocated
to the properties adjacent to the drain in the Community of Erie
Beach and the outlet assessment distributed to all of the lands
contributing water to the project. For Part 2, the reconstruction
of the drain enclosure north of Towanda Blvd., the B/O Ratio was
50/50 (Benefit $16,330 + Outlet $16,330 = $32,660). The Benefit
was distributed with $8,000 assigned to each of the Washburn/Weedon
and Solomon properties and $330 to Towanda Blvd. The $16,330 outlet
assessment was assessed to the agricultural landowners to the north.
In response to a question by Mr. Asher with respect to the costs
of the 2005 report, the Engineer responded that the engineering
work was continuous and that, in his opinion, there was no actual
cutoff date between the 2005 and 2010 reports.
The Evidence
Kenneth Anderson (Roll # 1-038) (Pts lots 50,
126 & 124)
Mr. Asher called Kenneth Anderson to give evidence.
Mr. Anderson testified that they purchased their property in 1995
and at the time of purchase, the drain enclosure was in the ground
and covered, however, the contractor's excavator was still on site.
His main concerns were the inadequate allowance for land (section
29 of the Act) and that an allowance was not made for the value
of the existing drain enclosure (section 31 of the Act) which is
being incorporated into the Report.
With respect to the section 29 allowance (land), he believes that
the agricultural land north of Erie Beach is worth $10,000 per acre,
however, residential property in Erie Beach is worth $139,000 to
$169,000. He testified that his property, which has a frontage of
100 feet on Towanda Blvd. and 50 feet at the beach, was appraised
in 2010 at $150,000. Mr. Anderson feels that the section 29 allowance
is not sufficient because the Engineer used a land value that was
too low.
Mr. Anderson believes that the Engineer should have provided a section
31 allowance for the existing drain when preparing his Report. He
testified that the purchase price of his property included the $26,000
cost to the property for the drain enclosure.
On cross examination by Mr. Courey, Mr. Anderson denied having any
knowledge that the $26,000 installation price was actually reduced
by a grant from the LTVCA. Mr. Anderson accepts the Engineers statement
in the Report that the drain enclosure on his property has an additional
15 year life. He stated that he should be compensated accordingly.
Mr. Anderson acknowledged that he did get a building permit for
construction of his garage and under cross-examination he admitted
that he was probably aware that the garage may have been constructed
over part of the drain. He also testified that if the pipe were
to fail, he would not be responsible for the drain and acknowledged
that although he has said in the past that he would fill it in,
he is not sure that he would.
Ross Brush (Roll # 10-502 and others)
Ms. McGuigan Kelly called Ross Brush as her first witness on behalf
of the upstream agricultural appellants.
Mr. Brush owns agricultural property immediately north of the Erie
Beach subdivision and immediately west of the Story Drain. The water
from that property drains into the Erie Beach Drain along the north
limit of the subdivision which outlets into the Story Drain. Mr.
Brush is a longtime resident of the area and farms approximately
600 acres in the area. Mr. Brush testified that since 1987 there
has been flooding in the Erie Beach area and that in early February
of this year water flowed continuously for 36 to 48 hours over Towanda
Blvd. Mr. Brush stated that, in his opinion, the proposed alternate
outlet location "would be a big zero" and that there is
no chance of putting all of the water through that proposed watercourse.
Mr. Brush objected to the 75% outlet allocation for the agricultural
land assessments.
Under cross examination by Mr. Courey Mr. Brush admitted that he
was aware that if the water leaves his land and erodes a neighbour's
property he is responsible. He maintained that there was significant
erosion in the past but the culvert that was installed is too small.
George Girty (Pt. Lot 6 W.C.R.)
Ms. McGuigan Kelly called George Girty as a witness on behalf of
the upstream agricultural appellants.
Mr. Girty is also a longtime resident of the area and has been an
unpaid superintendent of the pump station located at the outlet
of the Beaver Creek Drain at Bisnett Road since the early 1960s.
Mr. Girty testified that the alternate drain outlet as proposed
by Mr. Kuntze "can not work". He stated that the water
level of Lake Erie can vary as much as three feet and that winds
from the south require flood gates at the pump station to control
the back flow of water. Mr. Girty believes that the proposed alternative
would require an expensive pump station and raising the elevation
of the road at the proposed outlet.
James P. Bourne (lots 95 & 95 - north side
of Towanda Blvd.)
Ms. McGuigan Kelly called James Bourne as a witness on behalf of
the upstream agricultural appellants.
Mr. Bourne owns property on the north side of Towanda Blvd. just
east of the watershed for the Story Drain. He has lived in Erie
Beach his entire life, was a municipal councillor for a number of
years and was Reeve of the village until the amalgamation with Chatham-Kent.
Mr. Bourne stated that he was very familiar with the history of
the Story Drain. As a kid in the mid-1960s he used to jump it and
by the early 1980s it had grown in width of 25 to 30 feet across
at some points.
He testified that the drain enclosure through the Erie Beach subdivision
was constructed north of Towanda Blvd. in 1987 and south of Towanda
Blvd. in 1994. In 1987 the (LTVCA) provided a grant for the construction
of the portion north of Towanda Blvd. and the Municipality of Erie
Beach acted as the contractor. In 1994, while he was Reeve of the
Village of Erie Beach, further work was needed south of Towanda
Blvd. because what is now the Anderson house was in jeopardy and
in danger of falling into the creek. A similar arrangement was made
with the LTVCA for construction of the lower section of the drain
enclosure. Mr. Bourne testified that the letter from the LTVCA dated
October 17, 1994 outlining the cost to the abutting land owners
and the LTVCA grants were correct according to his recollection.
Mr. Bourne also recalled that Mr. Anderson had appeared before
the municipal council with respect to the construction of his garage
and that the Village of Erie Beach granted approval on the condition
that if anything were to happen to the garage later, it would be
Mr. Anderson's responsibility. A further requirement was that the
garage be built on a concrete pad and that there was no footing
below the surface.
John McGuigan (Roll # 10-610) (Pt. lot 8 Con WCR)
Ms. McGuigan Kelly called John McGuigan as a witness on behalf
of the upstream agricultural appellants.
Mr. McGuigan operates 657722 Ontario Inc., a company that owns
property in the extreme north of the watershed. He testified that
he was the spokesman for the agricultural appellants and provided
a document of authorization.
Mr. McGuigan stated that the upstream agricultural landowners are
objecting to the project because they had a sufficient outlet through
the natural watercourse which was filled in by the enclosed culvert
and now they are being told that it is no longer a natural waterway.
He testified that they now have to pay for it and do not think that
they should pay anything.
He also stated that since the enclosed culvert was installed, that
they have derived no significant benefit, and, in fact, there has
been increased flooding. He testified that the upstream landowners
feel that they have been dealt with unfairly in this endeavor.
He also testified that at the Court of Revision, his outlet assessment
was reduced because of the acreage of gravel extraction that was
removed from the assessment area. He clarified that the gravel lease
agreement for gravel extraction covers approximately 35 acres and
that he believes that approximately 15 acres have been extracted
at this point in time.
Raymond Dobbin, P.Eng.
Ms. McGuigan Kelly called Ray Dobbin as a witness.
Mr. Raymond Dobbin, the principal of R. Dobbin Engineering Inc.
from Petrolia, presented evidence on behalf of the agricultural
appellants. Mr. Dobbin was accepted as an expert witness by all
parties and the Tribunal.
Mr. Dobbin first testified with regards to the 2005 engineering
report costs that were included in the 2010 Report. He agreed with
Mr. Kuntze's analysis that the cost of the failed petition should
be distributed under section 10(4) if the report is not adopted
by Council. It was his opinion that those costs should not be assessed
under section 78 in the 2010 Report. Mr. Dobbin reviewed the assessments
in the Report first for Part 1 followed by Part 2.
Part 1 is the incorporation of the drain enclosure into the Story
Drain. The total cost of this part is $19,200 with $7000 to be assessed
as benefit and $12,640 being assessed as outlet. This results in
a Benefit/Outlet Ratio of 36/64 with 59.2% of the cost being assessed
as outlet to the owners upstream of the Erie Beach subdivision.
With respect to maintenance of Part 1 of the project downstream
of Towanda Blvd., the Report specifies 50% of the cost to be assessed
to the landowners where the work is done and 50% to the upstream
owners, proportioned in accordance with Schedule A-1 which includes
only the owners north of the Erie Beach subdivision. Mr. Dobbin
testified that agricultural land should be assessed only for drain
improvements necessary for the outlet of agricultural runoff. He
testified that there is no set rule regarding the percentage of
benefit, however, if this was an access culvert the B/O Ratio was
generally 50/50. He considers this project as a drainage enclosure
as opposed to an access culvert and the B/O Ratio should not be
50/50. He testified that as a result of this, it is his opinion
that the B/O Ratio for Part 1 should be increased from 36/64 to
a B/O Ratio of 67/33 for both the assessment levy for this Report
and for future maintenance.
The cost estimate for Part 2 is $32,660 with $16,330 assessed as
a special benefit and $16,330 assessed as outlet. This gives a B/O
Ratio in schedule A-2 of 50/50. Mr. Dobbin testified that he would
use a B/O Ratio of 67/33 as well for Part 2 for both the assessment
levy in this Report and for future maintenance.
Mr. Dobbin noted that the 2005 report prepared by Mr. Dries provided
a B/O Ratio of 75/25 for future maintenance.
Mr. Dobbin testified that a section 31 allowance for incorporating
the existing drain as outlined in the Act states that the allowance
shall be made. It is his opinion that the allowance for the existing
structure should be based on the original net cost to each land
owner and depreciated to today's value.
With respect to Mr. Kuntze's evidence about the alternate outlet,
he testified that he would have to study the proposed scheme before
he could make a comment.
On cross examination by Mr. Courey, Mr. Dobbin agreed that he did
not have an issue with respect to the design of the project as presented
and that his only issue was with the assessments.
In reply to a question from the Tribunal, Mr. Dobbins stated that
special benefits are not pro-ratable and that he would reduce the
special benefit assessments in the Report to zero and replace them
with a regular benefit assessment in accordance with section 22
of the Act.
Ed Dries, P.Eng.
Mr. Courey called Ed Dries as a witness for the Municipality.
Mr. Ed Dries, P. Eng., of Dillon Consulting Limited, in Chatham,
presented evidence on behalf of the Municipality. Mr. Dries was
accepted as an expert witness by all parties and the Tribunal.
Mr. Dries testified that there are two parts of his Report. Part
1, is the incorporation of the private drain in Erie Beach into
the Story Drain, and Part 2 is the construction of the drain enclosure
north of Towanda Blvd. He stated that the cost of Part 1 was estimated
at $19,640 and the cost of Part 2 was $32,660. He stated that, in
his opinion, for Part 1 which is the drain incorporation, the $19,640
should be assessed at a Benefit/Outlet Ratio of 36/64. He stated
that for Part 2, the drain enclosure, is similar to the replacement
of an existing culvert and that he assessed a special benefit assessment
to the adjacent landowners of 50% of the cost and assessed the remaining
50% to the upstream landowners (B/O Ratio of 50/50). He testified
that after hearing the testimony of the other engineers that he
would not change his methodology.
Mr. Dries agreed with Mr. Kuntze that the cost of $13,760 for the
pipe proper in his Cost Estimate in the Report was low and should
be corrected.
With respect to the engineering costs of the 2005 report being
included in the 2010 Report, it was his opinion that it was not
a failed petition. Mr. Ellis signed a petition, the report was prepared
and later referred back to resolve issues. A further report was
prepared to investigate alternate outlet locations into Lake Erie
and that the work was continuous up to and including the 2010 Report.
He testified that in the absence of a signed document that Mr. Ellis
had withdrawn, there was no mechanism to assign the cost to Mr.
Ellis. In the meantime, the portion of the drain enclosure north
of Towanda Blvd. failed and something had to be done and the 2010
Report was prepared under section 78.
With respect to the report dated March 30, 2007 on the alternate
outlet locations, Mr. Dries testified that none of the three alternatives
seemed practical and only Option 1, which outlets into Beaver Creek
and required a pump station was feasible. However, even this option
was not economical. He agreed with Mr. Girty regarding the work
necessary in raising the road in the Bisnett Road area. He stated
that the upstream owners are not looking for a new outlet and he
believes that they do have some fiduciary responsibility to the
existing outlet.
Mr. Dries discussed his methodology in determining the allowances
to be paid to landowners. For allowances for land, under section
29 of the Act, he stated that he used a width of 10 metres and a
land value of $10,000 per acre. For allowances for damages under
section 30, he provided a nominal allowance to the Solomon and Washburn
properties of $100 each because the works will result in complete
restoration of the properties. For the allowance for incorporating
the existing drain enclosure under section 31, he stated that he
had considered this and he did not believe that they were eligible
for an allowance.
Mr. Dries testified that the current drain proposal meets the Design
and Construction Guidelines for a 2 in 5 year storm, where the previous
open channel provided for a 1 in 50 year storm. He agreed that the
upstream landowners have definitely lost something in the process.
In response to questioning from Ms. McGuigan Kelly, Mr. Dries agreed
that the Benefit/Outlet Ratio of 75/25 in his 2005 report was much
closer to Mr. Dobbin's opinion and that he had put significant weight
on the downstream landowners. Ms. McGuigan Kelly suggested that
the Tribunal now has a fourth opinion in front of them and she believes
that Mr. Dobbin's 2005 opinion is fairer to the agricultural landowners.
Mr. Dries stated that one of the reasons for changing the B/O Ratio
in the 2010 Report was that the issue of public safety had been
raised and that these public safety issues went away when the drain
was enclosed. Mrs. McGuigan Kelly suggested that the public safety
issue was not the responsibility of the agricultural landowners
and that the B/O Ratio should not have been changed. Mr. Dries responded
that this was his reasoning and it was now up to the Tribunal to
decide.
In response to a question about assigning a benefit assessment for
all residents in Erie Beach as Mr. Kuntze suggested, Mr. Dries testified
that he would not consider it in this situation. He stated that
the Story Drain had functioned prior to being enclosed and he does
not believe that the residential property owners had any real issue
with the drain except for those abutting it.
Mr. Dries agreed with the reduction in assessed acreage for the
gravel extraction for the McGuigan property, and it was his recommendation
that the assessment schedule be modified by the Tribunal to accept
the Court of Revision decision in this respect.
In response to a question by Ms. McGuigan Kelly, Mr. Dries disagreed
that section 14(1) of the Act applied in this situation as the Report
provided for the replacement of an existing drain.
In response to a question by Mr. Asher regarding the section 31
allowance for the existing drain, Mr. Dries maintained that he did
address it and decided not to include it. He said that under the
Act there is no duty to include it, particularly if he did not think
it was justified. He further testified that he totally disagreed
with Mr. Kuntze's opinion and that he came up with a value of zero
for this allowance.
On a further question by Mr. Asher regarding the alternate drain
outlets referred to in the report dated March 30, 2007, Mr. Dries
testified that the report was requested by the Municipality and
that a general discussion of the options and the costing contained
in the report took place at the site meeting in 2009. Mr. Dries
confirmed his opinion of the costing of Option 1 in the report which
indicated that the cost of reconstructing the pump facility at Bisnett
Road could easily be in the range of $200,000 to $250,000. Mr. Dries
stated that, in his opinion, the alternative that Mr. Kuntze was
suggesting to redirect the flow easterly along the Robertson Drain
to a gravity outlet at Beaver Creek, would not work.
With regards to the 2005 engineering costs allocated to the 2010
Report, Mr. Dries testified that the work on the project under section
78 had been continuous since the original instructions were received
for the 2005 report. When Dillon Consulting purchased Todgem &
Case, all of the drainage works and projects continued on seamlessly.
Upon redirect from Mr. Courey, Mr. Dries confirmed that he chose
not to provide a section 31 allowance for incorporating the existing
works, and he believed that this still fulfilled his obligations
under the Act. He further explained that the $10,000 figure used
for the section 29 allowance was consistent with the principles
identified in his paper on allowances.
On questions from the Tribunal, discussion took place regarding
the Benefit Assessment and Special Benefit assessment. Mr. Dries
stated that page 10 of the Report indicated that the Special Benefit
Assessments in A-2 are pro-ratable assessments for this project.
Regarding the section 29 allowance, Mr. Dries replied that he chose
the $10,000 figure, not the full allowance or property value, and
by doing so he settled on a number that he thought was fair and
equitable.
On redirect from Ms. McGuigan Kelly regarding the 2005 report costs,
Mr. Dries stated that a considerable amount of the work for the
2005 report was used in the 2010 Report, however, he conceded that
there is a portion in the fees that relates solely to the 2005 report.
Ruth Wilson (lots 53, 54, 118 & 120)
Mrs. Wilson asked to make a statement to the Tribunal. She stated
that her family has had a cottage in Erie Beach for 47 years. She
stated that the drainage ditch started as an intermittent stream
with heavy flow in spring and after storms, and otherwise was a
cesspool and health hazard. She is very happy to have it enclosed.
Summations
Mr. Asher
Mr. Asher stated that Mr. and Mrs. Anderson are seeking an order
to have the Report referred back to deal with the issues of this
hearing.
With respect to the section 29 allowance for right-of-way, Mr.
Dries assigned the Anderson property an allowance of $837 based
on a land value of $10,000 per acre. Mr. Anderson calculated an
allowance value of $38,000 based on current real estate values and
asked that the Tribunal order the Engineer to obtain a market value
appraisal for the right-of-way.
With respect to the section 31 allowance for incorporating the
existing enclosure on the Anderson property, Mr. Dries did not consider
this allowance. Mr. Kuntze gave a value of $22,800 based on the
current replacement cost of the structure. Mr. Dobbin stated that
the original value of the structure, depreciated to 2010, should
be used.
He stated that Mr. Kuntze did not have strong objections to the
assessment in Schedule A-1 and that his suggested alternative would
include a benefit assessment against all of the residential properties
within the watershed in Erie Beach. Mrs. Wilson gave a statement
with respect to the improved aesthetic value to the subdivision
by having the drain enclosed.
Mr. Asher stated that Mr. Dries did not address the alternate outlet
locations in his Report and that Mr. Kuntze presented an alternate
outlet location through the Beaver Creek Drain which would not require
a pump station at this road.
Mr. Asher requested that the cost of the 2005 report prior to 2010
not be included in the Report and that it should be paid by the
Municipality. He also requested that the engineering and legal costs
for his client be added to the cost of the drain.
Ms. McGuigan Kelly
Ms. McGuigan Kelly agreed with Mr. Asher that the costs related
to the 2005 report should not be borne under the current Report.
She said her clients do not want an increase in the section 29 allowance
and that the request to explore the alternative drain outlets should
not proceed at the expense of the upstream properties.
She stated that there are now three engineers, with four opinions,
of what the B/O Ratio should be with the following percentages assessed
as outlet by the different engineers.
- Dries 2005 report - 25% outlet
- Dries 2010 report - 64% outlet for Part 1 and 50% for Part 2
- Dobbin - 33% outlet
- " Kuntze - 60% outlet
It is her submission that this drain enclosure is not a culvert
installation and should not be assessed as a culvert. The benefit
assessment for this drain enclosure should be higher than 50%.
She stated that for section 29 allowances, Mr. Dobbin agreed with
the values in the Report, and that an allowance for right-of-way
based on fair market value of the entire property does not make
sense.
Ms. McGuigan requested that the Tribunal order the following;
- the assessable acreage in Schedules A-1 and A-2 for Roll # 10-
610 (657722 Ontario Inc.) be reduced from 80 acres to 50 acres.
- a benefit assessment be added to the lands in the community
of Erie Beach.
- in Schedules A-1 and A-2, the benefit assessment be increased
to 67% and the outlet assessment reduced to 33%.
- the future maintenance of the drain enclosure south of Towanda
Blvd. be levied against the property on which the work is carried
out and the remaining 33% assessed against the upstream lands
in the same proportions as the outlet assessment as adjusted in
Schedule A-1.
- the future maintenance of the drain enclosure north of Towanda
Blvd. be levied in accordance with Schedule A-2 as amended.
- the Report be amended such that the addition of any surface
features that do not affect the drain, be assessed to the affected
owner.
- there be no change in the section 29 allowance in the Report.
- there be no section 31 allowance, but should the Tribunal award
any allowance, that the award be nominal.
- surface features such as a garage or other features that do
not affect the function of the drain be the responsibility of
the individual land owner.
- the engineering and contingency cost apportioned to the private
drain incorporation and set out in page 8 of the Report be reduced
by $11,179.
- there be no investigation with respect to changing the location
of the drainage works at the expense of the drainage works.
Ms. McGuigan Kelly stated that there is no basis for having Mr.
Anderson's legal and engineering costs included as part of the project.
However, if the Tribunal were to award costs to Mr. Anderson, she
would ask for her clients' costs be included as well.
Paul Courey
Mr. Courey first dealt with the appeal with respect to the design
of the project under section 48. He stated that Mr. Dobbin had no
concern for the design of the project, yet Mr. Kuntze challenged
the value of the allowances under both section 29 and 31, and maintained
that there is a better outlet for the agricultural water from the
Story Drain by improving the Beaver Creek Drain to the east to outlet
by gravity at Bisnett Road. Mr. Courey stated that literally generations
of engineers including Mr.
McGeorge, Mr. Todgham, and Mr. Dries, have worked on the Story
Drain and none have recommended an alternate outlet to Lake Erie.
Even Mr. Girty, a longtime landowner, who has operated the pump
station at the Beaver Creek outlet, has stated that the gravity
outlet proposed by Mr. Kuntze will not work.
Mr. Courey also commented on Mr. Kuntze's statement that he had
only made a cursory examination of the site just prior to the hearing.
Mr Courey said that the Municipality's position is to support the
Report as written and that there should be no further study of alternatives.
He further stated that the section 29 allowance for right-of-way
is for the use of the land and not for land taken, and that there
is a huge difference between the two. It is also the Municipality's
position that there should be no changes to the allowances as shown
in the Report.
Mr. Courey stated that the Municipality agrees with the submission
that the McGuigan property (Roll # 10-610) should be reduced in
area to 50 acres as proposed by the Court of Revision due to gravel
extraction. He stated that the Municipality proposed that the value
of the pipe used in the Cost Estimate in the Report should be corrected
from $13,700 to $21,600.
Request For Costs
Mr. Courey requested that the Tribunal order the appellants, Kenneth
and Lynda Anderson, to pay $2000 in costs to the Municipality.
Mr. Courey submitted that the need for two and a half days of hearing
time which included three lawyers, three engineers, and numerous
hours of municipal staff time to prepare for the Hearing, was largely
due to the Anderson's appeal. Mr. Courey noted that despite the
fact that the Andersons were greatly benefiting from the project,
they still launched this very costly appeal.
Mr. Courey also addressed the issue of Mr. Asher's Motion stating
that it was misguided and that he had informed Mr. Asher on a number
of occasions that his approach was wrong. He therefore asked that
$1000 of the $2000 requested be awarded as a deterrent to this kind
of inappropriate behaviour.
He concluded that the Municipality believed the upstream owners
had a reasonable complaint which they dealt with appropriately at
the Hearing through their legal counsel and, as a result, no costs
were being requested of them.
Mr. Asher responded by stating the Andersons were simply exercising
their right of appeal pursuant to the Drainage Act. He argued that
the Motion was properly brought forward and no penalty should be
addressed as a result.
Ms. McGuigan did not respond to Mr. Courey's submissions with regard
to the issue of costs.
Findings
The Tribunal reviewed the matter of the allowances for right of
way under section 29 of the Act and accepts the arguments that the
allowance is for right of way and should not be based on the real
estate value of the complete parcel of land. The Tribunal accepts
Mr. Dries' opinion and will not order a change in the section 29
allowance.
With respect to the section 31 allowance for including the existing
drain enclosure south of Towanda Blvd., the Tribunal rejects Mr.
Kuntze's opinion that the value of the existing drain enclosure
on Mr. Anderson's property should be the replacement value of a
new pipe depreciated by 50%. As an analogy, one would not value
a 1987 automobile based on the list price of a similar 2011 model.
The Tribunal accepts the opinion of Mr. Dobbin and Mr. Kuntze that
the Act requires the Engineer to provide a section 31 allowance
for the existing drain enclosure. Mr. Dobbin testified that the
allowance should be based on the original cost of the enclosure
to the owner of the land and depreciated. While Mr. Dries stated
that he had considered a section 31 allowance for Mr. Anderson and
had assigned a value of zero, there was no evidence in the Report
to indicate that. The Report stated that the drain enclosure south
of Towanda Blvd. appeared structurally sound with an anticipated
additional life of 15 years. No evidence was submitted to support
that statement and the estimates offered by the various parties
ranged from 5 to 20 years. No estimates were provided for the present
value of the drain enclosure. In light of the above, the Tribunal
will order a nominal allowance to the two landowners south of Towanda
Blvd. for the existing drain enclosure under section 31.
The idea of removing the present Story Drain outlet from the residential
subdivision of Erie Beach has been considered by engineers for the
past several decades. The most extensive study was described in
Mr. Dries' report dated March 30, 2007 where three options were
studied and all were rejected as not being feasible or economical.
The alternative proposed by Mr. Kuntze is similar to Option 1 of
Mr. Dries' report, however, Mr. Kuntze would not require a pump
station at Bisnett Road. The Kuntze proposal was rejected by all
of the other parties. The Tribunal finds that the Kuntze proposal
did not take into consideration the variation in the elevations
of Lake Erie, and was not based on sound engineering principles,
and, as such, should not be considered further. The Tribunal will
order that the outlet of the Story Drain in the existing location
as proposed in the Report is confirmed.
Considerable discussion took place regarding the disposition of
the engineering costs associated with the 2005 report. The Tribunal
accepts Mr. Dries' statement that the work from the 2005 report
was continuous, including the 2007 report on the alternatives and
the 2010 Report. In the cross examination of Mr. Dries by Ms. McGuigan
Kelly, he stated that there was a portion of the engineering work
that related solely to the 2005 report. On this basis, the Tribunal
finds that a portion of the engineering costs should be removed
from the Report and the Tribunal will order a nominal amount of
these engineering costs be charged to the Municipality.
During the course of the hearing, Mr. Dries and Mr. Kuntze agreed
that item 2 in the cost estimates on page 7 of the Report for the
supply of the pipe was too low and should be increased from $13,670
to $21,600. The Tribunal will order that correction.
Mr. Anderson testified that he was probably aware that his garage
may have been constructed over the drain. Section 5 of the specifications
in the Report provides for the relocation of the drain around the
garage on the Anderson property (Roll # 1-038) if necessary. Ms.
McGuigan Kelly in her summation requested that additional costs
due to the garage should be charged to the individual land owner.
The Tribunal will order that any additional cost of shoring up or
damage to the garage on the Anderson property shall be charged to
Roll # 1- 038.
Section 54(3) of the Act states that every appeal shall be heard
by the Tribunal by way of a new hearing and, as such, the Court
of Revision decision no longer applies.
The Court of Revision dated June 22, 2010 reduced the acreage assessed
on Roll # 10 - 610 (657722 Ontario Inc.) from 80 acres to 50 acres.
It ordered the assessment on that property be reduced by $406 in
Schedule A-1 and $585 in Schedule A-2 and that the corresponding
amounts be added to the assessments for Towanda Blvd. Mr. Dries
agreed with Ms. McGuigan Kelly that this part of the Court of Revision
decision should stand, and the Tribunal will so order.
One of the main issues before the Tribunal was that of assessment
and there were many points of view expressed. One of the points
of contention was whether the pipe was a culvert (a short length
of pipe to pass vehicles over the drain and transport water) or
a drain enclosure (a long length of pipe to only transport water).
Mr. Dries maintained that the pipe north of Towanda Blvd. was a
culvert and should be assessed using a B/O Ratio of 50/50 which
is generally accepted practice for assessing culverts. Mr. Dobbin
maintained that the pipe is a drain enclosure and that the benefit
assessment should be higher. The Tribunal accepts Mr. Dobbin's opinion.
Mr. Kuntze outlined an alternative assessment method which involves
placing a benefit assessment on each of the residential lots within
the watershed of the Story Drain based on the philosophy that all
of the residential properties receive a benefit by having the water
course through the subdivision enclosed. This proposal was supported
by Ms. McGuigan Kelly and by Mrs. Ruth Wilson, a resident of Erie
beach who expressed the benefit of having the previous eyesore covered
up when the drain was enclosed. Mr. Dries was opposed to this type
of assessment. On cross examination of Mr. Dries by Ms. McGuigan
Kelly on why his B/O Ratio had changed from 75/25 in the 2005 report
to 25/75 in the 2010 Report, his only response was that at the public
meetings, the issue of public safety was raised and that all of
the safety issues went away when the drain was enclosed. This argument
would suggest that the residential properties have a benefit by
having their safety issues resolved by the enclosed drain.
Considerable discussion took place regarding the appropriate B/O
Ratio for the assessments. As stated by Ms. McGuigan Kelly in her
summation, we have three engineers with four opinions. Mr. Dries
holds the extreme opinion with a B/O Ratio of 75/25 in the 2005
report and 25/75 in his 2010 Report. Mr. Dobbin is in between with
a B/O Ratio of 67/33 and Mr. Kuntze recommended a B/O Ratio of 40/60.
The Tribunal considered the matter of the B/O Ratio in great detail
and will order amendments to the Benefit/Outlet Ratio for the construction
and maintenance for both Parts 1 and 2.
The Tribunal will order that the Benefit/Outlet Ratio for assessments
in both Part 1 and Part 2 shall be Benefit 60% and Outlet 40%. Each
of the 54 residential properties listed on the "Small Parcel
Ownership Plan on Sheet 2 of 4 of the Report Drawings shall be assessed
$100 as part of the Benefit assessment in Part 1.
The Tribunal will order that the future maintenance of Part 1 shall
be assessed 50% to the adjacent landowners, 10% to the residential
properties, and 40% to the upstream landowners.
With respect to the Request for Costs, section 98 of the Act empowers
the Tribunal to award costs in any proceeding as it deems proper.
Section 17.1 of the Statutory Powers and Procedure Act also provides
that the Tribunal can order costs of a proceeding where a party's
conduct has been unreasonable, frivolous or vexatious or where a
party has acted in bad faith or where the Tribunal has created its
own rules of procedure governing the awarding of costs. Rule 28
of the Tribunal's Rules of Procedure sets out the circumstances
upon which the Tribunal may determine whether or not the awarding
of costs is warranted. Rule 28.04 states as follows:
Circumstances in which Costs Order May be Made
28.04 Clearly unreasonable, frivolous, vexatious or bad faith conduct
can include, but is not limited, to:
- Failing to attend a hearing event or to sending a representative
when properly given notice, without contacting the Tribunal;
- Failing to give notice or adequate explanation or lack of co-operation
during pre-hearing proceedings, changing a position without notice,
or introducing an issue or evidence not previously mentioned;
- Failing to act in a timely manner or to comply with a procedural
order or direction of the Tribunal where the result was undue
prejudice or delay;
- Conduct necessitating unnecessary adjournments or delays or
failing to prepare adequately for hearing events;
- Failing to present evidence, continuing to deal with issues,
asking questions or taking steps that the Tribunal has determined
to be improper;
- Failing to make reasonable efforts to combine submissions with
parties of similar interest;
- Acting disrespectfully or maligning the character of another
party; and
- Knowingly presenting false or misleading evidence.
The Tribunal will consider the seriousness of the misconduct.
If a party requesting costs has also conducted itself in an unreasonable
manner, the Tribunal may decide to reduce the amount awarded.
(The Tribunal will not consider factors arising out of a mediation
or settlement conference except where, for example, it finds that
a request for change to a settlement is unreasonable.)
The awarding of costs is a relatively rare occurrence and is not
a standard Tribunal practice. The Tribunal will analyze whether
the party in question acted "clearly unreasonable" during
the appeal process to the degree that a reasonable person would
deem that conduct to be unfair to the other parties involved.
Although we understand the Municipality's concerns with the length
of the Hearing process we find no facts to substantiate that the
Andersons acted in a "clearly unreasonable" fashion in
bringing forward and arguing their appeal.
We likewise find that although Mr. Asher's Motion on behalf of
the Andersons may have been somewhat misguided and brought forward
due to a lack of knowledge with respect to the Drainage Act, there
is no evidence before us that it was brought forth in a frivolous
or vexatious manner.
The Tribunal therefore denies the request to award costs.
Tribunal Order
- The Tribunal hereby orders as follows:
That the engineering costs of Part 1 (private drain incorporation)
be decreased by $3,900 and that this amount be paid out of the
general account of the Municipality.
- That an Allowance be provided for the existing drain in accordance
with section 31 of the Act in the amount of $2,600 for Roll #
1-038 (K. & L. Anderson) and $1,300 for Roll # 1-03701 (D.
& L. Ellis).
- That the Cost Estimate on page 7 of the Report for the supply
of the pipe be increased from $13,670 to $21,600.
- That the Engineer shall modify the Estimate of Costs on page
7 of the Report and the cost of Part 1 (drain incorporation) and
Part 2 (drain enclosure) on page 8 to reflect the above Orders.
- That the assessment on Roll # 10 - 610 (657722 Ontario Inc.)
in the existing Report be reduced by $406 in Schedule A-1 and
$585 in Schedule A-2 and that the corresponding amounts be added
to the assessments for Towanda Road.
- The Engineer shall then amend Schedules A-1 and A-2 in the Report
as follows:
- For Part 1 (drain incorporation) the Benefit/Outlet Ratio
shall be Benefit 60% and the Outlet 40%.
- The 60% Benefit shall be levied $100 for each of the
54 residential properties listed on the Small Parcel
Ownership Plan on Sheet 2 of 4 of the Report Drawings,
and the remainder proportioned to the lands assessed
for Benefit in Schedule A-1.
- The 40% Outlet shall be proportioned to the lands
assessed for Outlet in Schedule
- For Part 2 (drain enclosure) the Benefit/Outlet Ratio shall
be Benefit 60% and the Outlet 40% proportioned to the lands
assessed for both benefit and outlet in Schedule A-2 using
the amended cost estimate.
- That the outlet of the Story Drain in the existing location
as proposed in the Report is confirmed.
- That the Report be amended to provide for the assessments for
future maintenance on the section of drain enclosure extending
from Towanda Blvd. to Lake Erie. Future maintenance shall be levied
as follows:
- 50% to the lands on which the works are carried out.
- 10% shall be levied equally to the 54 residential properties
listed on the "Small Parcel Ownership Plan on Sheet 2
of 4 of the Report Drawings.
- 40% shall be proportioned to the lands assessed for outlet
in Schedule A-1.
- That any additional cost of shoring up or damage to the garage
on the Anderson property(Roll # 1- 038) due to the presence of
the Story Drain, shall be charged to that property.
- That there be no order as to costs and all parties are responsible
for their own costs.
- The non-administrative costs of the Municipality with respect
to this appeal shall form part of the cost of the drainage works.
Dated at Amherstburg, Ontario this 1st day of June, 2011