Dans cette section |
Courey Drain - New Access Bridge Extension
Si vous désirez obtenir une traduction de cette décision ou ordonnance, veuillez communiquer avec le bureau du Tribunal (voir ci-dessous). In the matter of the Drainage Act R.S.0. 1990, Chapter D.17, as amended.And in the matter of: An application to the Agriculture, Food and Rural Affairs Appeal Tribunal by the Town of Lakeshore under Section 58(4) of the Drainage Act to correct an error in the engineer's report for a New Access Bridge Extension over The Courey Drain, in the Town of Lakeshore. Before: Kirk Walstedt, Chair; Jack Young, Vice-Chair Decision of the TribunalThe Town of Lakeshore (the Municipality) applied to the Agriculture, Food and Rural Affairs Appeal Tribunal (the Tribunal) for an order under Section 58(4) of the Drainage Act (the Act) to amend By-Law 74-2009 to provide for a correction to the construction work. This application was considered by way of a written hearing, based on written submissions by the applicant and the engineer. BackgroundThe Courey Drain report (the Report) prepared by Dillon Consulting Ltd. (the Engineer), dated April 27, 2009, provides for an access bridge extension in an open channel located in Lot 19 Concession S.M.R in the Town of Lakeshore (formerly the Township of Tilbury North). The previous report on the Courey Drain, prepared by Todgham and Case, dated September 3, 2004, provided for the construction of the culvert that is the subject of the present report. The Report provides for a 4.0 metre extension to the 800mm corrugated steel pipe along with erosion protection. The total cost of the project was assessed to property roll number 650-05100 (Middle Road Farms Ltd). The provisional by-law was passed by the Municipality on July 14, 2009. Statutory ContextSection 58(4) of the Drainage Act states as follows:
The IssueThe issue before the Tribunal is:
SubmissionsIn November 2009, Mr. Paul Courey, representing Middle Road Farms Ltd., made a request to the Municipality to correct the location and length of the access bridge on lot 19. The purpose of the access bridge is to service wind turbines. The location of the access road to the turbines changed during the design process for that facility and after the drainage by-law had been passed. Mr. Courey stated that " This is a request that Council make a request to the Tribunal under section 58 (4) to make an order amending the report and adopting by-law so as to provide for the removal of the existing culvert and relocation and extension of it, some 30 m to the west. There is no adverse impact on anyone, nor are there any cost consequences to other parties." The Municipality passed a resolution dated December15, 2009 that "
Council directs Tom Marentette, Dillon Consulting to complete a submission
to the Ontario Drainage Tribunal under Section 58(4) of the Drainage Act
for the Gengrowth Wind Farm Access Culvert over the Courey Drain."
Analysis and Findings
|
Ce site est mis à
jour par le gouvernement de l'Ontario, Canada
© Imprimeur
de la Reine pour l'Ontario,
Dernière mise à jour :