Exeter Municipal Diversion Drain 2009In the matter of the Drainage Act R.S.0. 1990, Chapter D.17, as amended.And in the matter of: Appeals to the Agriculture, Food and Rural Affairs Appeal Tribunal by R. & D. Hamather and G. & J. McBride, of Exeter, Ontario, under Subsection 48(1) of the Drainage Act, from the engineer's report on the Exeter Municipal Diversion Drain 2009 dated April 21, 2009 in the Municipality of South Huron. Before: John O'Kane, Vice Chair; Enio Sullo, Member; and Sharon Weitzel, Member Appearances: Paul Courey, counsel to the Municipality of South Huron Decision of the TribunalThis hearing was held in the Municipality of South Huron Council Chambers, in Exeter, Ontario, on January 18 and 19, 2010. R. & D. Hamather and G. & J. McBride appealed to the Agriculture, Food and Rural Affairs Appeal Tribunal (the Tribunal) under Section 48(1) of the Drainage Act (the Act) from a report titled "Exeter Municipal Diversion Drain 2009" (the Report) prepared by Dietrich Engineering Limited and signed by W.J. Dietrich, P.Eng. (the Engineer) dated April 21, 2009. Mr. Michael Di Lullo, Manager of Corporate Services/Clerk of the Municipality, (the Clerk) performed the duties of the Clerk of the Tribunal. BackgroundThe Report proposes the construction of a new, closed municipal drainage system (the Works) on rural agricultural and golf course land, immediately adjacent to and along the easterly urban-rural boundary between the Town of Exeter and Township of Usborne, which are both parts of the Municipality of South Huron (the Municipality). The proposed Works will intercept and collect runoff from a predominantly agricultural watershed of approximately 96 acres (38.9 hectares). The estimated cost of the project is $1,474,700. The appellants Hamather and McBride (Appellants) are both the owners of the agricultural lands that comprise most of the watershed. They appealed to the Tribunal under section 48 of the Act, asserting that the benefits from the works are not commensurate with the estimated costs, the allowances provided by the engineer are inadequate and unreasonable in the circumstances, and such other grounds as their counsel may advise. Preliminary MattersPrior to the hearing, the Tribunal issued an order making all landowners assessed or compensated in the Report parties to this Hearing. The Clerk filed an affidavit of service proving that all assessed or compensated landowners on the Exeter Municipal Diversion Drain 2009 had notice of the hearing, and satisfied the Tribunal of the requirements of section 99 of the Act. Also prior to the hearing, the Tribunal received an application for party status from Peter Aunger, a resident of the Municipality neither assessed nor compensated in the Report. At the hearing, Mr. Aunger explained that he is a property owner on Sherwood Crescent in the Town of Exeter, adversely affected by flooding since about 1980. He supports the Works and is concerned that further delays could result in the loss of about $890,000 funding from the Province. There were no objections to Mr. Aunger's application. Accordingly, after a short recess to consider the matter, the Tribunal granted Mr. Aunger party status. The Issue(s)
The DecisionAs explained below we find that the benefits of the proposed Works are not commensurate with the estimated costs and accordingly grant the appeal and set aside the Report. The Evidence - Administrative ProcessThe Clerk's Record documents the administrative process. On October 16, 2006, the Council of the Municipality (Council) passed the following Resolution directing the Road Superintendent to sign a drainage petition and appointing Mr. Dietrich to investigate construction of a municipal drain to divert flood water into the Ausable River.
On October 23, 2006, the Road Superintendent signed a Petition for Drainage Works under Section 4 of the Act. On May 5, 2008, Council passed a further resolution providing:
The Engineer testified that Council gave him written instructions to prepare a report under the Act. He said the instructions did not stipulate preparation of a Preliminary Report, so he prepared the Report as a final report. The written instructions from Council are not in evidence. On May 19, 2009, Council considered the Report. Minutes of that Council meeting refer to Mr. Dietrich in some instances as the Drainage Superintendent and in other instances as the Drainage Engineer. The Council minutes also contain an Addendum to the Report comprising five items, four of which alter the Works which also change the Section 29 allowances. Council adopted the Report and Addendum by the following resolution: "THAT South Huron Council receive the Exeter Municipal Diversion
Drain 2009 Report and Addendum to the Engineer Report as prepared by W.J.
Dietrich, P.Eng., Dietrich Engineering Limited and set the Court of Revision
for Monday, June 15, 2009" The Report does not contain a Schedule of Assessment but instead assesses the entire cost of the Works to the Municipality. The Engineer testified that the Municipality agreed to accept all the costs of the Works and so he assessed the Municipality accordingly. He testified that he believed the assessment complied with the Act. The Engineer also testified that no other reports were produced aside from the Report which is the subject of this hearing. The Evidence - Design and Location of the WorksThe Report contains information on the investigation undertaken by the Engineer and details of the recommended Works, including construction drawings and specifications. The Engineer was qualified to give expert opinion evidence in drainage engineering. He elaborated on the Report during his testimony at this hearing. According to the Engineer, for many years the areas along the eastern part of Exeter have received uncontrolled runoff from predominantly agricultural properties to the east, often resulting in flooding of certain roads, residences and businesses along the flow path during various rainfall and snow melt events. The flooding has caused significant disruption and damage, particularly to immediately downstream roads and dwellings. The watershed contributing to the runoff comprises approximately 96 acres (38.9 hectares) of primarily undeveloped agricultural land, which includes the lands owned by the Appellants. The only exception is a small residential strip along the north side of Huron Street that currently drains into a closed tile drain known as the Huron Street Drain. That tile drain outlets into the Exeter storm sewer system and is too small to drain surface runoff. The incidence of flooding of the downstream, built-up areas of Exeter was confirmed by the evidence of Mr. Aunger and his witnesses and was uncontested by the Appellants. The Engineer investigated several alternatives to provide the petitioned
flood relief. One alternative was to upgrade the storm sewer system in
Exeter, including the construction of a new, enlarged storm sewer along
portions of Eastern Avenue, extending downstream to the Ausable River.
However, he discarded that alternative because of excessive cost, time
and disruption to the community, as well as it not being practically feasible
due to conflicts with existing sewers and utilities within the road rights-of-way.
That alternative also required additional property since the Eastern Avenue
right-of-way does not extend down to the Ausable River. As a result, the
Engineer directed his attention to the concept of diverting the runoff
to the north along the Exeter/Usborne boundary. He considered several
alternative locations and design variations. He analyzed each alternative
for cost effectiveness, feasibility, impact on adjacent land and the ability
to satisfy the design objectives. On completing his analysis, the Engineer,
in consultation with the Municipality, the Ausable River Conservation
Authority and the landowners, selected the location and design provided
in the Report. The Engineer explained that he used a 100-year storm design standard for the design of the drain. While acknowledging that this is an unusually high design standard for a municipal drain, he believes the design standard is necessary in this case. He confirmed that in his entire professional practice he had never before designed a municipal drain to a 100-year storm standard. The Appellants did not present any engineering evidence. Counsel for the Appellants challenged the Engineer about the drain route on the Appellants' lands, including the construction of surface features such as catch basins, berms, rock erosion protection and grassed buffer strips. The challenge was that those structures would take land out of productive agricultural use. Counsel for the Appellants also challenged the Engineer on the basis that the Works are required strictly for the benefit of urban land within Exeter and will be a detriment to the agricultural lands. Counsel for the Appellants suggested to the Engineer that the storm drain can be constructed along an alternate route, more specifically along Eastern Avenue. Counsel for the Appellants was unable to alter the Engineer's opinions during cross-examination. The Appellants asked the Engineer to comment on a $1.6 million cost estimate prepared by another engineering firm, Gamsby and Mannerow Limited, for a storm diversion drain along Eastern Avenue. The Engineer testified that the estimate was incomplete because it only included the portion of the drain on the Eastern Avenue right-of-way and did not include ancillary costs such as property acquisition, relocation of utilities, interest, inflation, legal services, surveying, easements and other miscellaneous costs. He estimated the additional cost of the downstream portion of the drain, beyond the Eastern Avenue right-of-way, at about $600,000. He declined to estimate the ancillary costs because he was not convinced it is feasible to construct the Works along Eastern Avenue amid the existing sewers and utilities. Additionally, he testified that there would still be the cost of the surface works such as catch basins, berms, rock erosion protection and grassed buffer strips on the Appellants' lands as well as branch drains to direct the runoff to Eastern Avenue. During cross-examination, the Engineer acknowledged that the agricultural
lands might not see a change to their drainage after construction of the
Works because their surface runoff is currently draining away unimpeded
onto the downstream urban lands. However, he disagreed with the Appellants
that they would not receive any benefit from the Works. Mr. Aunger and his two witnesses testified that they and their neighbours have been adversely affected by flooding since they moved into their homes. In Mr. Aunger's case, this was since 1980. Mr. Aunger presented a number of photographs depicting the flooding events as well as detailed flood data that he collected over the years. He stated that the supported the Works and asked the Tribunal to dismiss the appeals and allow the work to proceed. The Evidence - Planning Act versus Drainage ActUnder the rubric of "such further and other grounds as counsel may advise" set out in paragraph 4 of the Appellants' Notice of Appeal dated June 30, 2009, Counsel developed an argument that the Report ought to be set aside as being contrary to the Planning Act and Provincial Policy Statement (PPS). Counsel for the Appellants argued that the proposed Works are new storm water management facilities benefiting urban lands. He asserted that the Works would divert water away from the urban area of Exeter through his clients' agricultural lands. He argued the Works provide no benefit to the agricultural use of the lands for the raising of crops or livestock. He suggested that the proposed use of the Appellants' agricultural lands for urban infrastructure is a land use planning matter because it proposes to change the land use from agriculture. He argued that because of that the Planning Act and the PPS prevail over the Drainage Act. The Appellants' argument flows from the paramountcy provision in section 71 in the Planning Act entitled "Conflict" which states:
The Drainage Act does not contain a paramountcy clause. Mr. William Pol was qualified as an expert witness in planning and provided testimony for the Appellants. Mr. Pol testified that the Tribunal, in exercising any authority that affects a planning matter, must make its decision consistent with any applicable policy statement. He pointed out that this requirement is mandated by clause 3(5)(a) of the Planning Act. He then took the Tribunal through the PPS in effect since March 1, 2005. The essence of Mr. Pol's evidence is that using the Appellants' agricultural lands for construction of the Works changes the land use from agricultural use to urban infrastructure use. He testified that is contrary to the PPS policy objective of preserving prime agricultural areas such as the Appellants' land for long-term agricultural use. Mr. Pol further testified that the proposed Works must also comply with the Official Plan and Zoning Bylaw for the Municipality of South Huron. He testified it is contrary to those planning instruments to remove lands from agricultural production for urban storm water management facilities. In cross-examination, Mr. Pol conceded he had never reviewed the Drainage Act. Mr. Pol testified that in his professional career he had not previously encountered a case where the Planning Act, or the PPS, had prevailed over the Drainage Act. The Engineer also testified that he had completed approximately 700 reports under the Drainage Act over his 30-year career and that he too had never heard of the Planning Act applying to drainage works. He also had not heard mention of such at any of the meetings and conferences of the professional associations to which he belongs. Counsel for the Appellants asked the Tribunal to set aside the drainage report because the proposed Works are not consistent with the Planning Act and the PPS and the Official Plan. Findings and Analysis - Administrative ProcessThe Municipality's and Engineer's apparent disregard and cavalier attitude toward the provisions of the Act disturb the Tribunal. The following list details multiple instances of non-compliance or disregard of the Act throughout the administrative process:
Findings and Analysis - Design and Location of the WorksAlthough the Report refers to alternative drainage solutions investigated there are few details provided on these alternatives in the Report. While the Act does not specifically mandate including such details, they would have been extremely useful and helpful in understanding the Engineer's final recommended Works and may have even assisted the parties in resolving their differences. Despite the lack of detail in the Report, the Tribunal is satisfied with the location and routing of the drain as recommended by the Engineer. The uncontested evidence is that the source of the runoff that causes the flooding in the urban area is predominantly from the agricultural lands, including those of the Appellants, with the exception of a small residential strip along Huron Street. That flooding is the impetus behind the Petition for Drainage. Although a small portion of the Appellants' lands outlet to the Huron Street Drain, the majority of their lands drain overland toward the downstream urban areas in Exeter. Under Common Law, downstream landowners and roads are not obliged to accept runoff from upstream lands and roads. Faced with overland water flow, downstream landowners might use self-help remedies or lawsuits based in nuisance law against the upstream owners. Upstream landowners need a legally protected outlet. A landowner achieves a legally protected outlet by containing and directing their runoff to a Municipal Drain constructed under the Act or to a Natural Watercourse. In the circumstances before us, the upstream landowners who are the Appellants McBride and Hamather have no legally protected outlet for the bulk of their drainage. We accept the Engineer's evidence that the drain route will convey the
overland water flowing off the agricultural land to a sufficient legal
outlet. We also accept the Engineer's evidence that the drain will provide
improved sub-surface water controls to the McBride and Hamather lands,
which is a benefit to their agricultural activities. The Engineer has designed the drain to a 100-year standard. That standard is based on the rainfall and run-off associated with a hypothetical storm event that occurs only once every 100 years. This is an unusually high standard for a municipal drain. One of the Panel members is a retired professional engineer and drainage engineer with over thirty years professional experience in drainage. In that Panel member's experience, he has never seen a 100-year standard for a municipal drain. The Engineer testified that the proposed design standard is much higher than the current 5-year standard for the storm sewers in the Town of Exeter. He confirmed that most urban storm sewers are designed to a one in five-year storm event and said that in his professional career he had never previously designed a municipal drain to a 100-year standard. In response to questions from the Panel, he testified that if he had used a typical design standard for municipal drains, the cost of the project would probably be about one-quarter of the cost currently proposed. He also confirmed that had he used any other standard less than the 100-year standard, the projects costs would likely go down by about half. (emphasis added) Based on the evidence about the unusual design standard and the resulting impact on the costs of the Works, the Tribunal is not satisfied that such a design standard is warranted for a drain that conveys water run-off from primarily agricultural lands. In the absence of a Cost Benefit Statement under Section 7 of the Act,
the Appellants have satisfied us on their appeal ground number 1 that
the benefits to be derived from the proposed drain design are not commensurate
with the estimated costs. Findings and Analysis - Planning Act versus Drainage ActDrainage is an integral and necessary part of successful agriculture. The Appellants have enjoyed good drainage of their lands for many years by allowing the surface water to flow downstream lands within Exeter. The Tribunal is satisfied on all the evidence that the source of the runoff is predominantly from agricultural lands, including those of the Appellants. Therefore, we find the proposed Works will benefit the Appellants' lands for their continued use growing crops and livestock. We also find the proposed Works are not storm water management facilities for the sole benefit of the urban lands within Exeter. Under Common Law, the Appellants have no assurance they can continue to discharge runoff onto downstream lands and roads. The Tribunal is satisfied that an appropriately designed drainage works is necessary for the Appellants' agricultural land use to collect and direct runoff from the agricultural properties to a good and sufficient outlet in the Ausable River. Accordingly, the Tribunal finds that an appropriately designed drainage works is not a land use planning matter that engages the Planning Act and the PPS. Order of the TribunalThe Tribunal orders that:
Dated at Brampton, Ontario, this 8th day of March, 2010. For more information: Toll Free: 1-888-466-2372 ext. 63433 Local: 519-826-3433 E-mail: appeals.tribunal.omafra@ontario.ca
|
|||||||