In This Section |
Brown/Iona Road Drain
In the matter of the Drainage Act R.S.0. 1990, Chapter D.17, as amended.And in the matter of: An appeal to the Agriculture, Food and Rural Affairs Appeal Tribunal by Paul Brown and Nancy Brown, in Fingal, Ontario, under Subsection 48(1) of the Drainage Act from the engineer's report on the Brown/Iona Road Drain in the Municipality of Dutton/Dunwich, Ontario. Before: Kirk Walstedt, Chair; Jack Young, Vice Chair; Claire Belluz, Vice Chair Appearances: Wybe Cnossen, P.Eng., on behalf of the Municipality of Dutton/Dunwich,
respondent Decision of the TribunalBackgroundThe report on the Brown/Iona Road Drain in the Municipality of Dutton/Dunwich (the "Municipality") was initiated by a petition signed by Mr. Robert Brown in accordance with Section 4 of the Drainage Act, R.S.O. 1990, c.D.17 (the "Act"). The Municipality appointed Wybe Cnossen Engineering Ltd in accordance with Section 8 of the Act to examine the area requiring drainage and prepare a report. The report titled "Brown / Iona Road Drain" dated November 27, 2007 (the "Report"), was signed by Wybe Cnossen, P.Eng. (the "Engineer"). Mr. Paul Brown and Ms. Nancy Brown ("P & N Brown") appealed to the Tribunal under subsection 48(1) of the Act, from the Engineer's Report. The reasons for P & N Brown's appeal were that:
The P & N Brown appeal was heard on Thursday, May 22, 2008, in Dutton, Ontario. Mr. Ken Loveland, Clerk for the Municipality performed the duties of the Clerk of the Tribunal. Prior to the Hearing, the Tribunal issued an Order making all landowners assessed or compensated in the Report parties to the appeal. Mr. Loveland filed an Affidavit of Service at the start of the Hearing, as evidence that the Notice of the Hearing was served on all parties. Mr. Paul Brown attended the Hearing on behalf of P & N Brown, both of whom were represented by Mr. John Wiebe, P.Eng., with CJDL Consulting Engineers. The work outlined in the Report is intended to provide a drainage outlet
for the property owned by Robert and Jean Brown (Roll # 007-102), by construction
of a new tile drain beginning on their property, and continuing parallel
to Iona Road, along the front of Paul P & N Brown's property (Roll
# 007-103). The drain will cross Iona Road to outlet in a natural watercourse
on Neil Brown's property (Roll # 002-002). The project will consist of,
470 metres of tile drain, 36 metres of pipe road crossing, four (4) catchbasins,
and rip-rap erosion protection at the outlet. The estimated cost of the
project is $28,468.00. The Engineer produced an assessment schedule that
divided the estimated costs of the Drain among four privately owned properties
in the watershed, as well as to the Municipality and to the Township of
Southwold ("Township"). The Municipality and the Township were
the only assessed landowners to receive special benefit assessments. The IssuesThe issues before the Tribunal were:
An issue raised in the letter of appeal, with respect to the validity of the petition, was withdrawn. The EvidenceMr. John Wiebe, P.Eng., on behalf of P & N Brown, gave the Tribunal a brief overview of his background as a drainage engineer. Mr. Wiebe presented speaking notes with a map entitled "Watershed Plan" attached. He also made reference to a previous submission to the Tribunal, a package with a covering letter dated May 5, 2008 from CJDL Consulting Engineers, received by the Tribunal. Mr. Wiebe told the Tribunal that P & N Brown do not have a drainage problem on their property and that their appeal is based on the view that their property:
Mr. Wiebe stated that the only reason for P & N Brown's property to be included in the Report is for their property to be connected to a municipal drain and to have a legal outlet. He told the Tribunal that the Brown property should not be assessed for benefit and he presented a document containing a proposal of his opinion of how the assessments should be distributed. The Engineer told the Tribunal that the new tile outlined in the Report
is to be installed 10 feet inside P & N Brown's property line, and
that if they were to need access to the Drain, they would have the opportunity
to connect three (3) to four (4) runs of tile to the Drain. He added that
although P & N Brown's property is well-drained, it will receive benefit
from having access to a tile with greater capacity than their current
system. Mr. Wiebe requested that the overall assessment to P & N Brown's property be reduced to thirty percent of its current assessment for outlet, leading to a change in the total assessment to their property, from $1,869 to $220. In response to questions from the Tribunal, the Engineer stated that: there are no municipal drains adjacent to the Brown/Iona Road Drain; and that the topography of the area was such that the watershed boundary was determined by visual observation. Mr. Paul Brown told the Tribunal that the sugar maple tree originated on their property and grew outward, into the road allowance. Mr. Brown further told the Tribunal that he feels he should receive compensation in the amount of $1,044 for the loss of sap production from this tree, due to damage it will incur during construction of the project. The Engineer referred to a letter from Brian Vaughan, an Ontario Land Surveyor, stating that the tree is located two (2) feet on to the road allowance. He also said that some of the tree's branches have been cropped due to their proximity to hydro lines. In response to a question from the Tribunal, Mr. Brown stated that the sugar maple tree is not being tapped for syrup production at this time. In response to questions from the Tribunal, the Engineer stated that: it would be feasible to route the tile at a farther distance from the tree than outlined in the Report; and that in the Report, the tile is approximately 12 to 15 feet (3.5 to 4.5 metres) from the tree. Mr. Brown told the Tribunal that the roots of a sugar maple tree extend laterally at a distance that is roughly equivalent to the height of the tree. He added that to avoid damaging the roots, the tile would need to be approximately 60 feet away. Mr. Wiebe requested that the compensation to P & N Brown's property for damages leading to expected death of the sugar maple tree be in the amount of $250. Mr. Wiebe also requested that the Drain be moved a distance of 10 metres farther from the tree, than outlined in the Report, as well as for an widened road crossing, from 18 metres to about 23 metres. He estimated that the net increase to construction costs resulting from these proposed modifications would be in the amount of $200. The Engineer acknowledged that the proposed modifications can be done, and does not take issue with Mr. Wiebe's suggestions. With respect to the expected crop loss as a result of construction on the edge of P & N Brown's property, the Engineer told the Tribunal that he feels that P & N Brown have been adequately compensated. He added that, at a meeting with Mr. Paul Brown, Mr. Brown expressed concern about the impact of the construction of the Drain on his property. In response to questions from Mr. Wiebe, the Engineer told the Tribunal that his calculation of the compensation to P & N Brown's property was based on 2 years of crop failure over 50 feet of damaged area at a rate of $4 per metre. He added that it would not be unfair to double the compensation for damages to the Brown's property. The Engineer responded to further questions from Mr. Wiebe, in stating that: he is unaware of the current cost of soybeans; that the damage to P & N Brown's property will likely only be within 20 feet of the boundary; and that he is unsure of whether compensating P & N Brown for 3 years, if they were growing a more specialized crop, would be appropriate. Mr. Wiebe requested that the compensation to P & N Brown's property for damages leading to expected crop loss be increased to $2,631, for damages over three (3) years at a rate of $877 per year. Further, Mr. Wiebe requested that P & N Brown be compensated for damages to a laneway, in the amount of $300. The total compensation requested for P & N Brown is of $3,181. Mr. Robert Brown requested that his property be compensated at the same rate as P & N Brown's property, for damages leading to expected crop loss. Mr. Wiebe proposed to the Tribunal that, in order to achieve equitable compensation for expected crop loss, Mr. Robert Brown's compensation increase by $1,887. Mr. Wiebe further proposed that the increase in compensation to Mr. Robert Brown and Mr. Paul Brown, as well as the increased construction costs noted above, be distributed as follows:
The Engineer acknowledged that increasing the compensation to Robert Brown and to P & N Brown, on the basis of three years of crop loss, would not be out of order. He did, however, state that the increase in compensation would need to be assessed to others. With respect to the request for damages to P & N Brown's laneway, during the construction of the Drain, the Engineer told the Tribunal that any damages can be repaired by the contractor at the time of construction, and that he does not feel compensation for the laneway is in order. The FindingsThe Tribunal has reviewed the evidence with respect to the potential damage to the sugar maple tree. While the tree is located on the municipal road allowance, it has been used in the past for maple syrup production; however, it has not been taped recently. The evidence is not compelling that the construction of the project would destroy the tree or that any landowner should receive compensation for a tree that is located on municipal property. The Tribunal notes the acceptance of the parties to relocate the drain further away from the tree and will not grant any compensation for the tree. The Tribunal has considered the evidence and arguments with respect to the amount of allowances granted to the appellants and finds that the allowances in the Report are fair and equitable. With respect to the assessments on the appellants, P & N Brown's
property (Roll # 007-103), the Tribunal finds that there is a benefit
to their property to have an improved and legal outlet for their existing
drainage system across the municipal road and also for the additional
capacity to connect some of their field tile directly to the new tile.
The Tribunal will confirm the appellants' assessments as shown in the
Report. Order of the TribunalAfter consideration of the evidence filed and the submissions made the Tribunal orders:
Dated at Maidstone, Ontario, this 19th day of June, 2008. For more information:Toll Free: 1-888-466-2372 ext. 63433 Local: 519-826-3433 E-mail: appeals.tribunal.omafra@ontario.ca |
This site is maintained
by the Government of Ontario
Queen's
Printer for Ontario
Last Modified: