In This Section |
Nutrient
Management Protocol
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Author: | OMAFRA Staff; Ministry of the Environment |
|---|---|
| Creation Date: | 12 August 2005 |
| Last Reviewed: | 12 August 2005 |
The Regulation requires that the design and construction of a new permanent nutrient storage facility or an expansion, or alteration of an existing permanent nutrient storage facility or part thereof shall be carried out by or under the supervision of a professional engineer. The following Certificate will be required for any new or expanding operations where the regulation requires the oversight of an engineer.
There are several locations in the Regulation that rely on the dry matter content of manner. The dry matter content of manure can be establish through sampling, referring to Appendix 1 for average values or reference to the information that follows.
Average Dry Matter Values - To help determine whether manure has a dry matter content of (≥18 to <30%), (≥30 to <50%) or (≥50%), the following basic guidelines can be followed:
|
Project:
|
______________________________________________ Name/Location |
||
|
This is to Certify that I:
|
____________________ Owner |
____________________ Signature |
____________________ Date |
| understand that under the Nutrient Management Act,
2002, I am required to retain engineering services for specific
projects and situations. Therefore I have retained the following
Professional Engineer: |
|||
| ____________________ Engineer's name |
____________________ Signature |
____________________ Date |
|
|
to undertake the overall coordination and completion of the
engineering design and general review of construction; or |
|||
| Design Component | Engineer's Name | Engineer's Signature | Address | Phone |
|---|---|---|---|---|
| Site Characterization * - sub-surface information, soil properties, water table and bedrock location (if critical) | ||||
| Liquid Storage Facilities - drawings and design details for liquid storage construction | ||||
| Solid Storage Facilities - drawings and design details for solid storage construction if applicable | ||||
| Earthen Storage Facilities - drawings and design details for earthen storage construction | ||||
| Synthetic or Natural Liner - design details, including details of inspection and testing of seams. | ||||
| Transfer Systems - drawings and design details for connections, materials, etc. |
* Geoscientist retained to perform a Site Characterization evaluation must be a member of the Association of Professional Geoscientists of Ontario
| Top of Page |