Vegetated Filter Strip Design Manual
Design Guide


| Introduction and Background | General Design Guidance for VFS System Components |
| Design Guidelines of VFS System Components |
| Design Guide | Case Studies | Design Tables | Glossary |


| Runoff Collection Area | Storage Settling Basin | Runoff Collection/Discharge Bay |
| Conveyance Pipe | Distribution Pipe | Infiltration Area |



Design Guide
Conveyance Pipe

Step

Description

Method/Design Parameter

Equation Variables

Value

Units
4.1 Define target flow rate Target conveyance pipe flow rate is 10% greater than storage/settling basin discharge rate from Step 2.2.4 or 2.3.4.   Orifice discharge rate from storage/
settling basin increased by 10%
  m3/s
4.2 Establish minimum pipe/channel slope Establish minimum pipe/channel slope based on Manning's Equation (Equation 3.9). A=Q/V
D=(4A/3.14)0.5
R = D/4
S = (Vn/R2/3)2
A = area of pipe/channel   m2
Q = flow rate    
V = velocity of flow   m/s
D = diameter of pipe   m
R = hydraulic radius = area of water flow in pipe/channel divided by the wetted perimeter of pipe/channel; for circular pipe R = D/4    
S = minimum slope of pipe/channel   m/m
n = Manning's n, PVC Pipe (smooth inner walls)
0.009  
0.03  
4.3 Establish design variables for evaluation of conveyance system Establish the inlet elevation of the conveyance pipe/channel from the sump/drainpipe (gravity flow with adjacent infiltration area).   EINLET = Inlet elevation of conveyance pipe (from sump) or conveyance channel (from drainpipe)   m
Establish conveyance pipe/channel run length from sump/drainpipe to top of infiltration area.   L = length of conveyance pipe/channel run   m
Establish the elevation of the existing grade at top end of the candidate infiltration area.   EEXISGRADE = elevation at existing grade (at top end of infiltration area)   m
Calculate outlet elevation of the conveyance pipe.   EOUTLET = EINLET - (S)(L)    
EOUTLET = outlet elevation of conveyance pipe   m
S = minimum slope of conveyance pipe (see Step 4.2)   m/m
L = length of conveyance pipe run   m
Compare conveyance pipe outlet elevation with elevation of existing grade at top end of infiltration area. See Step 4.4.   EOUTLET = outlet elevation of conveyance pipe    
EEXISGRADE = elevation at existing grade at top end of infiltration area
(see Step 4.4)
   
Calculate elevation change between inlet elevation of conveyance pipe/channel from sump/drainpipe and elevation of existing grade at top end of infiltration area.   ECHANGE =
Einlet - Eexisgrade

ECHANGE = elevation change (represents lift for pump system or drop for gravity system)

   
4.4 Determine gravity or pump system If the existing grade at the top end of the infiltration area is lower than the conveyance pipe outlet elevation calculated, e.g., positive elevation change, then gravity flow to the top end of the infiltration area is possible. Rerun Manning's equation to ensure that slope between inlet elevation of conveyance pipe and existing grade at the top of the infiltration area generates a minimum pipe flow velocity of 0.6 m/s   Gravity flow    
If the existing grade at the top of the infiltration area is higher than the conveyance pipe outlet elevation calculated, e.g., negative elevation change, then gravity flow to the top end of the infiltration area is not possible. A pump will be required to transfer the runoff to the top end of the infiltration area.   Pumped Flow    
4.5 Determine target flow rate Target conveyance pipe flow rate is 10% greater than storage/settling basin discharge rate. See Step 4.1.   Orifice discharge rate from storage/
settling basin
  m3/s
  Target conveyance pipe flow rate (10% greater than orifice discharge rate from storage/settling basin)   m3/s
4.6 Determine total head losses between pump inlet and distribution pipe discharge Determine head differential.   Difference in elevation between sump/drainpipe and existing grade at top end of infiltration area (see Step 4.3)   m

To calculate pipe friction losses use Darcy -Weisbach Equation (Equation 3.8) with f = 0.020 or another equivalent method.

Friction losses = f(L/D)(V2/2g) Friction losses due to pipe run, including localized losses caused by pipe bends, valves, etc.   m
f = friction factor 0.020  
L = conveyance pipe length   m
D = conveyance pipe diameter   m
V = velocity of flow   m
g = acceleration due to gravity 9.8 m/s2
Add pressure head of 0.9 m at the distribution pipe.   Distribution pipe pressure head 0.9 m
Determine total head losses. Total head losses = head differential plus pipe friction losses plus distribution pipe pressure head     m
4.7 Select type and size of pump Select submersible sewage pump (preferably screw-induced flow) with automatic controls, capable of moving up to 24 mm solids. Obtain flow curves for selected pump and select the most efficient pump that will accommodate target conveyance pipe flow rate and head differential.   Manufacturer
HP
   
4.8 Determine pipe size required The pipe size must be sufficient to convey the target discharge rate output. Check that pipe velocity does not exceed 1.5 m/s and friction losses are acceptable.   Conveyance pipe diameter   mm
4.9 Determine requirements for power and controls Calculate distance from power source and effort required to power and automatically control pump.   Check pump requirements (110 V or 220 V, or other)    
  Contact consultant or electrical contractor for recommendations    

| Top of Page |

| Introduction and Background | General Design Guidance for VFS System Components |
| Design Guidelines of VFS System Components |
| Design Guide | Case Studies | Design Tables | Glossary |


For more information:
Toll Free: 1-877-424-1300
Local: (519) 826-4047
E-mail: ag.info.omafra@ontario.ca
Author: Robert P. Stone, P. Eng., Engineer, Soil/OMAFRA
Creation Date: 14 September 2005
Last Reviewed: 16 August 2007