Grid Connections: Techs & Specs
March 11, 2006
London, Ontario
Bob Singh, Manager - Generation Connections
Presentation Focus: what you need to know and do to connect to Hydro One's
distribution system
Renewable Generation includes:
- wind, solar, Bio-mass, Bio-gas, Bio-fuel, landfill gas, or water
- important part of Ontario's supply mix
- Hydro One initiatives in support of renewable energy:
- connection policies, processes & requirements
- working with government/OPA on RFP as well as Standard Offer Program
issues
- helping generation proponents with RFPs
Connection to Transmission or Distribution?
Transmission (Tx) 50 kV & higher
- Generator Must be Market Participant
- Requires IESO & Hydro One Assessments
Distribution (Dx) Under 50 kV
- Requires Hydro One (T & D) Assessment
- 110 MVA also requires IESO Assessment
Distribution System Code
Technical Process Contracts Costs
Generator Classification and Rating:
- Micro - </= 10 kW
- Small - </= 500 kW for system voltage < 15 kV; </= 1 MW for system
voltage >/= 15 kv
- Mid-Size - < 10 MW
- Large - >/= 10 MW
Connecting Very Small Generators
Residential Installations (e.g. Solar Panels)
- Distribution Generator Connection Process still applies (less onerous)
- Main Requirements:
- Isolation - Safety
- Auto-shutdown Feature - Safety
- ESA Approval - Safety
- Metering
Connection of Small Renewable Facilities - Net Metering
- Our policies for connection made easy and customer friendly
- Program offers opportunity to lower electricity bills
- residential, farm, and small business
- Focus is on small renewable generation technologies
- solar, wind, biomass, up to 500 kW
- No assessments under 50kW
- Continue to look at ways to speed up assessments
- Hydro One's Net Metering Policy is available at: www.hyroonenetworks.com/en/electricity_updates/renewable_technologies/
Process: Distribution Generation Connection
- Customer Request
- Hydro One Connection Assessment (Tx & Dx)
- Hydro One Design & Estimate
- Approvals and Connection Cost Recovery Agreement
- Construct
- Test
- Connection
Timeline Obligations per DSC
- Initial Consultation
- Small - 15 days
- Mid-Sized - 15 days
- Large - 15 days
- Connection Impact Assessment
- Small - 60 days* (no exp./rein.), 90 days* (exp./rein.)
- Mid-Sized - 60 days
- Large - 90 days (includes ESO assess.)
- Estimate
- Small - *Included in above
- Mid-Sized - 90 days
- Large - 90 days
- Total
- Small - 75 days to 105 days
- Mid-Sized - 165 days
- Large - 195 days
Generator Obligations for Hydro One Cost
- Initial Consultation
- Small - Free
- Mid-Sized - Free
- Large - Free
- Connection Impact Assessment
- Small - $ 3K
- Mid-Sized - $ 5K
- Large - $ 6K (does not include IESO fee)
- Estimate
- Estimate costs depend on the situation and vary from project to project
Who Plays a Part?
- Generator
- Hydro One
- OPA
- Electrical Safety Authority
- External Consultant
- Ministry of Environment
Ministry of Natural Resources
- Municipal Government
- OEB
- IESO
Electrical Safety Authority & Generator Responsibilities
Ensure:
- Public Safety with Generation facility
- Safety of Generator's workers
- Protection of Generator's assets
Generator must design the facility to prevent any negative impact on the Hydro
One system or other customers' electrical or communication equipment.
Hydro One Responsibilities
Ensure:
- Safety of Hydro One workers
- Protection of Hydro One assets
- No negative impact on Hydro One system and its customers (Security, PQ)
- Customer connection
Obligations consistent with:
- Market rules
- Applicable codes
- NPCC/NERC standards
To expedite connection of DGs, Hydro One has:
- Technical requirements in place to ensure safety, reliability, PQ and system
integrity.
- Websites in place for Net Metering and Government & OPA projects (e.g.,
RFP's and Standard Offer Program) - provide helpful information on processes
and activities involved
- Simple, customer friendly forms and templates have been created to expedite
assessments and cost estimates
- Customer handout is available - provides an excellent overview of what is
involved in connecting generation to the Hydro One grid.
Hydro One's other Initiatives to enable DG
- Current generation connection processes will be further streamlined
- Customer information package will include: simplified user-friendly forms
and detailed templates for assessments, expedited studies and cost estimates
- Continue interacting with the Ontario Government, OPA, OEB, CSA and other
stakeholder groups to ensure generation connections to the Hydro One grid
are made in a consistent, timely and cost effective manner.
For you to keep in mind ...
- Hire a qualified consultant to assist you with the processes and technical
requirements
- Involve all key players and provide them complete information
- Contact Hydro One early in the process