Table of Contents
- Introduction
- Causes of Gully Formation
- Design of a Control System
- Low Gradient Systems (0-25%)
- High Gradient Systems (greater than 25%)
- Construction of the Control System
- Maintenance of the System
Introduction
Throughout Ontario, especially in areas with deep sand plains, high
stream banks or long sloping valleys, extensive gully erosion problems
occur. Large quantities of valuable agricultural soils are lost each
year to gully erosion.
Gully erosion is an advanced stage of rill erosion where surface channels
have been eroded to the point where they can not be smoothed over by
normal tillage operations.

Figure 1. An active gully in a sand plain area.
Often, gullies can be prevented if good land conservation measures
are practiced on the farm. Good tillage and cropping practices increase
the absorptive capacity of the soil resulting in less run-off and also
protect the land surface from erosion. Surface and tile water should
be conveyed from lands through proper waterways so as not to create
potential gully problems. Buffer strips should be located at potential
gully start points such as open ditches or deep depressions.
The saying "A Stitch in Time Saves Nine" is also valid for
gully erosion control. Often a potential large gully problem can be
solved if discovered and controlled early in its formation.

Figure 2. A gully located on clay soil. A grassed waterway shown
in Figure 3 was used to solve this problem.
| Top of Page |
Causes of Gully Formation
Increase in flow of surface (or subsurface) water
An increase in water flow can be due to several reasons such as improvement
of drainage channels upstream, removal of water holding areas upstream
(such as a swamp or bush), enlargement of the watershed or a change
in tillage and cropping program in the watershed.
Decrease of soils resistance to erosion
There are several ways that a soils resistance to erosion can be reduced
such as elimination of a vegetative cover, breakdown of soil structure
due to poor tillage and cropping practices, constant saturation by a
trickling tile or compaction by tractor wheels.
Sloughing and mining at the bottom of the gully
Sloughing occurs at the base of a gully due to a strong spring, a constant
saturation of the area by a pond or the eroding power of a waterfall
from a higher to lower elevation, e.g. cultivated field to eroded channel.
As the undermining process continues, the gully head moves upstream
and enlarges in width and depth.
| Top of Page |
Design of a Control System
In the design of a control system for a gully problem the following
steps are to be followed.
(1) Inspect the gully to determine why the problem occurred; what possible
changes have taken place to aggravate the problem? Is there a spring
at the gully base?
(2) Estimate the peak flow of water entering the gully. This quantity
depends on the watershed's topography, size, vegetation, soil type and
water storage capacity. Technical expertise is required for this step.
(3) Measure the approximate size and slope of the gully.
After this information is obtained, a control system can be selected.
There are two types of control systems available: (a) the low to medium
gradient systems utilize soil linings, drop structures or a buried pipe
to run the water down the gully slope; and (b) the high gradient system
uses drop pipe inlets to carry the water to a satisfactory outlet.
| Top of Page |
Low Gradient Systems (0-25%)
Grassed Waterway
If the gully slope is small (less than 5%) and the available channel
is quite wide (more than 20 feet) a grassed waterway can carry a medium
to large flow of water.

Figure 3. An established grassed waterway controlling gully
erosion in a corn field.
Initial establishment of the vegetation can be a problem. Maintenance
practices such as fertilization and mowing of the vegetation as well
as land management practices above the gully area to prevent sedimentation
of the waterway are necessary for this control system to be successful.
Grassed Waterway With Drop Structures
If a channel slope is too steep (5-10%) for a grassed waterway, a series
of drop structures can be used to reduce the effective slope of the
waterway below the upper limit of 5% for a grassed waterway installation.
Drop structures can either take the form of a chute spillway or a grade
control structure.
-
Chute Spillways
Chute spillways are constructed with rock riprap, interlocking or cable­connected
concrete blocks or other materials and are designed to carry a concentrated
flow of water down an inclined structure.
Figure 4. A chute spillway absorbs the energy of the flowing
water.
They blend in well with grassed waterways since their shapes are similar.
These structures must be underlain with a filter cloth material.
-
Grade Control Structures
Grade control structures are a type of drop structure that reduces
waterway grade by providing vertical drops up to 3 feet at selected
locations along the channel .
Figure 5. Gabion basket grade control structures move water
down slopes.
There are two main types of grade control structures used in agriculture:
(a) the gabion basket type; and (b) the wood log type. These structures
should always be backed with a filter cloth material to prevent soil
from washing through and causing failure. For further information on
grade control structures see Factsheet Gabion Basket Drop Structures
Along Waterways.
Lined Waterway
If the channel slope is in the range of 10-25% throughout a significant
portion of its length, the entire steeply sloping section could be lined
with an erosion resistant material. Acceptable lining materials are
rock riprap, gabion mattresses and interlocking or cable-connected concrete
blocks. These structures must be underlain with a filter cloth material.
An inflexible channel lining such as poured concrete does not have the
ability to move with the base material shifts caused by settling, frost
heaving or possible erosion. Thus, concrete is not recommended as a
waterway lining.
The velocity of water exiting this structure may be excessive, causing
further erosion problems downstream. A deceleration device such as large
rock riprap may be required.
Surface Water Inlet and Buried Tile Line
A surface water inlet such as a catch basin or perforated riser pipe
connected to an underground tile line will remove run-off water from
small watersheds.
Figure 6. A perforated riser pipe which intercepts surface water
and moves it underground.
Most gully gradients are acceptable with this system; however, the
recommendations regarding maximum and minimum grades in OMAFRA Publication
29, Drainage Guide for Ontario should be adhered to. A clay berm should
be constructed slightly downstream of the surface inlet to pond the
water and allow the surface inlet to operate at full capacity.
When the topography of the land is suitable, a larger berm may be constructed
that will pond water for periods up to 24 hours.

Figure 7. A floodwater storage (water and sediment control basin)
holding back water.
The construction of this floodwater storage for smaller watersheds
(or water and sediment control basin) results in a significantly reduced
outlet tile size. Watershed areas up to 50 acres can feasibly be designed
using a floodwater storage system. Proper design of this system is critical
since failure could cause dramatic erosion problems.
| Top of Page |
High Gradient Systems (greater than 25%)
When excessive gully slopes are encountered, drop pipe inlet systems
provide acceptable solutions to erosion problems.
Drop pipe inlets are normally used for high drop, high gradient locations.
A concentrated flow of water is carried through an enclosed pipe structure
made of steel, plastic or concrete to a satisfactory outlet. Most of
the components of the drop pipe inlet, if steel or plastic, can be prefabricated
to reduce field construction time. A clay berm is constructed in conjunction
with the drop pipe inlet to allow the run-off water to pond at the intake
and force the pipe to flow at full capacity.
Figure 8. A drop pipe inlet system with a high berm to allow
temporary floodwater storage.
The structure should be constructed similar to a dam except instead
of holding water, it holds back soil. For further information on drop
pipe inlets see Factsheet Drop Inlet Spillways.
The following types of drop pipe inlets are commonly used in agriculture:
Drop Pipe Structure
This structure consists of a vertical pipe fabricated to a horizontal
pipe which is installed at approximately 1% grade to the outlet.
Figure 9. Sketch of drop pipe structure.
Although this type of drop pipe can handle elevation differences up
to 10 feet it is preferable to limit the drop height to 5 feet for safety
construction reasons.
High-Drop Inlet Structure
The high-drop inlet is similar to the drop pipe structure except that
the vertical pipe is about 5 feet high and the horizontal pipe follows
the surface of the gully once it intercepts with the gully face.

Figure 10. High-drop inlet structure with seepage drain.
This structure is used for steep gully drops greater than 5 feet in
height.
Sloped Pipe Structure
The sloped pipe structure consists of one component, a sloped pipe.
Figure 11. Sketch of a sloped pipe structure.
This type of structure may be used when drops exceed 5 feet.
Surface Water Inlet and Buried Tile Line
A perforated riser pipe or catch basin in conjunction with a buried
tile line can be used to convey run-off water from small watersheds
down steep slopes. This inlet system can be used for most gully drop
heights provided that the maximum grade recommendations for the tile
line as outlined in OMAFRA Publication 29, Drainage Guide for Ontario
are followed.
Figure 12. A perforated riser pipe and tile line being installed
The different drop pipe inlets have flow capacities that are dependent
upon the structure sizes. More than one drop pipe inlet system may be
used at one gully site to carry the design flow.
To increase the effective capacity of the drop pipe inlet system a
floodwater storage is often used. This storage will fill up with water
during peak flow periods and empty after the peak flow is over. If flood
storage is used, it is important to have an emergency spillway to convey
water down the berm if expected flow rates are exceeded; otherwise,
failure of the berm may occur.
| Top of Page |
Contruction of the Control System
Proper installation of the drop pipe inlet is important to ensure that
a future failure does not happen. Anti-seepage collars should be installed
on all horizontal pipes to prevent water from channelling along the
outside of the pipe. A well constructed clay berm that has been adequately
compacted around the pipes is imperative.
If groundwater seepage appears to be contributing to the problem a
seepage drain (Figure 10) should be constructed to
intercept the water flow from the spring. This seepage drain utilizes
a filtered tile or rock bed to drain out the water without moving the
soil.
The system should be constructed at a time when peak flow is not expected.
The vegetative cover must have time to become established in the channel.
A good set of plans and a well thought out sequence is very necessary.
| Top of Page |
Maintenance of the System
Any erosion control system needs regular attention to check and repair
weak areas before failure occurs. A checklist should he followed as
below:
1) Any bare or eroded area should be repaired immediately.
2) Obstructions or potential obstructions in the flow area should be
removed.
3) Any settling or shifting should be repaired.
4) All grassed areas should be mowed twice per year.
5) The inlet for the control system should be cleared of snow and ice
before the spring peak flows.
6) All berms should be checked regularly for signs of failure and remedial
measures taken.
Assistance
Technical assistance is available from the Agricultural Engineer at
the local office of the Ontario Ministry of Agriculture and Food. The
Conservation Authorities may offer both technical advice and construction
supervision in certain areas of the Province.
For the large gully projects that have a high capital cost and high
risk involved it is recommended that a Consulting Engineer be hired
for design and supervision of the project.
| Top of Page |