Constructing an Earthen Liquid
Nutrient or Runoff Storage Facility
We are updating this page to reflect current regulations.
Information on this page about regulations under the Nutrient Management
Act, 2002 and the Environmental Protection Act is out of
date. On September 18, 2009 new regulations affecting those applying non-agricultural
source materials on agricultural lands were filed. Please visit www.ontario.ca/nasm-omafra
for more information.
Table of Contents
- Introduction
- Scope
- Key Points
- Sizing
- Siting
- Setbacks Not Specified in the NMA Regulation
- Professional Involvement
- Specific Criteria Required by the NMA Regulation
- Appendix A: Site Characterization/Investigation Criteria
Specified in the Regulation
- Appendix B: Engineer Commitment Certificate - Form A
- Related Links
Introduction
The following document provides recommendations to address the construction
of an earthen liquid nutrient storage or runoff storage facility as required
by the Nutrient Management Act, 2002, (NMA) and the associated Regulation
O. Reg. 267/03 (as amended to O. Reg. 511/05). Figure
1 shows a lined, earthen storage facility.

Figure 1. This earthen storage facility has been equipped
with a secondary containment liner to provide additional protection for
surface and ground water.
Scope
This Factsheet applies to a permanent earthen storage facility having
either:
- 14 or more days of storage capacity (for the associated facility)
or
- a maximum depth of liquid nutrients of 100 mm (4 in.) or more.
Key Points
- Earthen nutrient storage facilities without any incorporated concrete
structure(s) are typically not deemed to be a structure in Ontario and
consequently do not require a building permit; however the Nutrient
Management Act regulates their siting and construction.
- At least 2 levels of underground protection are required for these
storage facilities.
- The above ground portion must have secondary containment or appropriate
landscape features.
- Most of the design must be carried out under the supervision of a
professional engineer. Some aspects of the design may involve a professional
geoscientist.
- Proper setbacks from sensitive features such as wells, surface water
and conflicting uses must be met.
- Any perforated tile drain close to the storage must be removed unless
it is required for a foundation drain.
- If any component of the facility is constructed of concrete, that
component must be designed and constructed using the concrete and steel
storage specifications (see OMAFRA Factsheet 06-001, Constructing
a Permanent Concrete or Steel Liquid and Runoff Storage Facility
or other applicable standards). This may trigger the need for a building
permit.
Sizing
For a regulated farm the minimum capacity of the storage must:
- include precipitation directly entering an open-top storage of 2.27
mm/day (example: if the storage is designed for 240 days of capacity,
the precipitation input should be 2.27 x 240 days or 0.55 m over
the surface area of the storage)
- include a freeboard1
of 0.30 m
- include 240 days of manure and bedding production2
from attached livestock facilities with the following exceptions:
- where the farmer sends some of the manure to a broker and the
aggregate storage capacity of the broker and the farmer is 240 days
(e.g. a layer chicken operation has an agreement with a broker who
can provide 60 days of storage. The manure storage at the layer
chicken operation would only need to be designed for 180 days)
- where the period of use of the barn is less than 240 days
(e.g. a beef feeder operation houses the animals for 180 days in
the barn from Nov. 1 until they go to pasture on May 1. The
manure storage would only need to be designed for 180 days)
- where the farmer's nutrient management plan permits lesser periods
of storage, (e.g. a NMP demonstrates that manure can be applied
at a frequency that is less than 240 days). NOTE: for liquid manure
storage this can only be used if the number of farm animals on the
farm unit has not increased since Sept. 30, 2003 or
- where the farmer's nutrient management strategy permits lesser
periods of storage via the use of transfers out of the farm unit
(e.g. a dairy farm transfers its manure off-site every three months
to another farm unit. The manure storage at the dairy farm would
only have to be designed for 3 months).
1 Freeboard is an additional depth
of storage required to deal with wave action due to wind or agitation
and to provide a safety factor to address unexpected circumstances (e.g.
excessive rainfall, leaks in water system, etc.). It is added to the calculated
depth required for manure production and precipitation.
2 The manure and bedding production must
be based on numbers shown in Table 3.1 of the Nutrient Management Protocol
(note MSTOR, a computer program developed by OMAFRA will include these
numbers and can be used to complete the calculations.)
Siting
The following distances (from the top of the inside sloping face of the
storage) must be met:
- Well setback - the NMA Regulation requires that any new or expanding
storage be at least:
- 15 m from a drilled well that has a depth of at least 15 m and
a watertight casing that extends to a depth of at least 6 m below
ground level
- 100 m from a municipal well and
- 30 m from any other well.
- Flow path requirement - the NMA Regulation specifies that a farm
constructing or expanding any nutrient or runoff storage, must be at
least 50 m away from surface water or a tile inlet or have a flow path
that is at least 50 m (165 ft.) long. The flow path is the distance
over ground any liquids would have to flow from the storage before entering
surface water or a tile inlet. This flow path does not always follow
a straight line as illustrated in Figure 2.

Figure 2. A flow path does not always follow a straight
line. This required flow path is used to provide opportunities for flow
control in the event of a spill.
- 1 in 100 Flood Line- The NMA Regulation requires the storage to be
constructed above any one in 100 year flood line established by a municipality
or conservation authority (if the municipality or conservation authority
has established such flood lines) unless a permit for the storage is
issued under Section 28 of the Conservation Authorities Act.
- Tile drains (field) - All perforated drains within 15 m (50
ft.) must be located, intercepted and removed. Any flow from a field
drainage system or piped municipal drain must be redirected away from
the storage.
- Tile drains (structural) - The following two options can be used
to manage water from a perforated foundation drain within 15 m of a
manure storage facility:
- any perimeter drain for the storage must run through an observation
and shutoff station prior to entering another drainage system or surface
water. This special catch basin has 2 purposes. It can be used to
detect leakage from the storage to the foundation drains. In addition,
it is used to shut off the flow and allow steps to be taken to identify
and deal with the leakage. Figure 3 shows a typical
observation and shutoff station used to provide access to the tile
drain.
- collect the foundation drain water and discharge it to a treatment
system.

Figure 3. An observation and shutoff station is used
to provide access to a perimeter drain if required. Possible contaminated
flow can be observed and blocked. Steps can then be taken to address the
situation.
Setbacks Not Specified in the NMA Regulation
Minimum Distance Separation (MDS II) Formula
- MDS II determines minimum separation distances between proposed new,
enlarged or remodeled livestock facilities and/or permanent manure storages
and other existing or approved development (e.g. neighbouring houses,
areas zoned residential, lot lines, road allowance, etc.)
- MDS II is triggered when a building permit is required, but because
earthen storages are not considered to be a building, they do not require
a building permit. However, this does not exclude them from the requirement
for siting according to the MDS formula. Best Management Practices recommend
the MDS formula be followed in all cases and this is backed up by the
Provincial Policy Statement, 2005, policy number 1.1.4.1 (c):
- 'New land uses, including the creation of lots, and new or expanding
livestock facilities shall comply with the minimum distance separation
formulae.'
- The term livestock facility is defined in the new MDS-2005 as:
- 'Permanent structures with livestock-occupied portions, intended
for the keeping or housing of livestock, including feedlots, and
containing one or more barns or structures, Includes manure storages,
whether associated with a livestock facility or not...'
- For more information, contact your Nutrient Management Consultant
or local OMAFRA engineer.
Other Municipal Setbacks
- Contact your municipality for more information on other required
setbacks
Professional Involvement
For the construction or expansion of a permanent liquid nutrient storage
facility [O. Reg. 267/03 [as amended to O. Reg. 511/05]] requires that
professionals complete the following:
-
Design - a professional engineer must complete the design, including
any monitoring system (if installed).
-
Site investigation - a professional engineer or a professional geoscientist
must carry out a site characterization assessment.
-
Supervision - the construction or expansion must take place under
the supervision of a professional engineer. This supervision process
has been shown to be very important in the construction of a liquid
manure or nutrient storage system.
-
Commitment certificate - the engineer must sign the Engineer's Commitment
Certificate (see Appendix B) prior to the construction. The farmer
must submit this with the Nutrient Management Strategy.
-
Additional requirements - other municipal and provincial requirements
may need to be addressed on a site-specific basis. For more information,
contact your local building official.
Specific Criteria Required by the NMA Regulation
- General design - the facility, including any associated plumbing
systems used to transfer manure or liquid nutrients, must be "designed
to minimize leakage, minimize corrosion and to be structurally safe
and sound." [O.Reg. 267/03 as amended: sentence 71. (1)(b)]
- Site requirements - There are two options for earthen, liquid nutrient
storage facilities:
- Option 1 - Storage for liquid agricultural source materials (excluding
manure): Must satisfy the criteria as specified in Figure
4. The Regulation specifies details regarding interior surface
treatment, soil anomalies and above-ground berm construction. For
example, the soils that form the inner surface must be disked to
a depth of 150 mm and recompacted to meet a hydraulic conductivity
of no more than 1 x 10-8 m/sec.
- Option 2 - Storage for liquid agricultural source materials (including
manure): Must satisfy the criteria as specified in Figure
5. In addition to the 2 m of hydraulically secure soil, this
option requires the installation of a compacted soil, geo-synthetic
or synthetic liner. Liner installation details are specified in
the NMA Regulation. For example, the Regulation specifies that:
- liners must be continuous under the storage facility and must
extend to a level equal to the surrounding ground surface, unless
the designer specifies otherwise.

Figure 4. Design criteria for smaller runoff storage facilities,
storing liquid agricultural source materials other than manure.
Figure 5. Design criteria for storage facilities,
storing liquid nutrients and/or manure.
- Compacted soil liner - if this type of liner is used it must be constructed:
- using a minimum of 6 layers, of 150 mm thick material on the
inside sloping surfaces
- using a minimum of 4 layers of 150 mm thick material on the floor
surface.
- Hydraulic conductivity - it is recommended that a liner should have
a hydraulic conductivity of no more than 1 x 10-9 m/sec.
- Site investigation - is required for all permanent, liquid nutrient
storage facilities. (See Appendix A)
- Secondary containment - If the liquid level in the storage facility
is partially or wholly above the surface of the surrounding soil, the
following options apply:
- a professional engineer can determine that the storage and landscape
features around the facility are adequate to ensure that a secondary
containment system is not required; or
- the designer incorporates a secondary containment system, with
a capacity of 110% of the above ground portion of the volume of
material stored.
- Transfer systems - all connections in a liquid transfer system must
be installed using specifically designed fittings and gaskets that are
compatible with the pipe material
- all pipes entering a liquid manure facility must have a flexible,
watertight gasket or membrane installed between the pipe and the
floor or wall of the storage structure to serve as an anti-seepage
collar
- any transfer system having an opportunity to backflow to the
pump or pump-out chamber must have both a primary and secondary
shutoff valve.
- Floor transfer systems - must be constructed of concrete and be capable
of containing and transferring liquid to a storage facility. A floor
transfer system does not include:
- areas within the barn, designed to house livestock, but not intended
to collect liquid manure
- areas under dairy free-stalls
- feed trough areas
- floors under manure pack areas.
- Ventilation - All covered storage systems must have a ventilation
system that may be either a powered or natural ventilation system to
prevent the accumulation of corrosive or noxious gases.
- Alternative design - An engineer can produce a design that is equivalent
to or makes use of materials that are equivalent to those referred to
in the Act or Regulation.
Appendix A: Site Characterization/Investigation Criteria
Specified in the Regulation
Site characterization is a process followed for all new, permanent liquid
manure storage structures to determine how much protection is provided
by the natural environment on the proposed building site. A basic site
characterization evaluation considers the soil type and water table location,
etc. In cases where the natural site does not provide sufficient protection,
it may be necessary to use a synthetic liner, a geo-synthetic liner or
an engineered soil (usually clay) liner to enhance the protection for
surface and/or ground water.
You must hire a professional engineer or professional geoscientist to
make the site assessment. OMAFRA can provide a partial listing of engineering
and geotechnical companies who are familiar with agricultural projects.
These individuals will take soil samples and investigate the location
of permanent and naturally or artificially occurring water tables. These
tests can be carried out using a boring machine or a backhoe/excavator.
The machine must be capable of boring or excavating to a minimum depth
of 1.5 m below the lowest excavation for the structure. If an earthen
floor is desired, the depth of investigation must be 2.5 m below the lowest
excavation for the structure. One borehole or excavation is required per
1,000 m2 of ground floor area for the facility being constructed.
The engineer or geoscientist may require more samples to be taken, due
to site conditions.
The soil samples must be evaluated by a geotechnical laboratory to determine
their physical properties. The geotechnical evaluation will determine
if the soil provides a level of protection equivalent to OMAFRA's guidelines.
These guidelines are listed below:
- The saturated hydraulic conductivity of the soil is a measure of
how rapidly water (and nutrients) can move through the soil. For protection
of the environment, slower is better. Hydraulically secure soil has
a maximum saturated hydraulic conductivity of 1 x 10-8 m/sec.
An indication of the saturated hydraulic conductivity of the soil can
be obtained by several means:
A professional geoscientist may alternatively provide data or a design
that will provide a level protection that is an equivalent to the above
alternatives.
An important part of a site characterization study is to determine the
level of the water tables in the vicinity of the proposed liquid nutrient
storage facility. There can be several water table levels on a building
site. Some of these occur naturally, while others may have been caused
by other construction projects. Constructing any part of a storage facility
below a water table is not advised. In some cases, a water table can be
artificially lowered by providing a drainage system surrounding the storage.
This drainage system would require a monitoring catch basin to show that
no direct contamination is occurring.
In some problem soils, the best alternative may be to make use of a synthetic,
geosynthetic or engineered soil liner to provide secondary containment.
With two levels of protection for the environment, the protection offered
by the proposed building site becomes less critical.
Appendix B - Engineer Commitment Certificate - Form
A
Project (Name/Location): ___________________________________________________________________
This is to Certify that I:
________________________
Owner
________________________
Signature
________________________
Date
understand that under the Nutrient Management Act, 2002, I am required
to retain engineering services for specific projects and situations. Therefore
I have retained the following Professional Engineer:
________________________
Engineers name
________________________
Signature
________________________
Date
to undertake the overall coordination and completion of the engineering
design and general review of construction; or
I have retained the following Professional Engineers to provide engineering
services for the following components of the engineering design and review
of construction:
| Design Component |
Engineers Name |
Engineers Signature |
Address |
Phone |
| Site Characterization * - sub-surface information, soil properties,
water table and bedrock location (if critical) |
|
|
|
|
| Liquid Storage Facilities drawings and design details for
liquid storage construction |
|
|
|
|
| Solid Storage Facilities drawings and design details for
solid storage construction if applicable |
|
|
|
|
| Earthen Storage Facilities drawings and design details for
earthen storage construction |
|
|
|
|
| Synthetic or Natural Liner design details, including details
of inspection and testing of seams. |
|
|
|
|
| Transfer Systems drawings and design details for connections,
materials, etc. |
|
|
|
|
Do you know about Ontario's Nutrient Management Act?
The provincial Nutrient Management Act (NMA) and the Regulation 267/03
regulates the storage, handling and application of nutrients that could
be applied to agricultural crop land. The objective is to protect Ontario's
surface and groundwater resources.
Please consult the regulation and protocols for the specific legal details.
This Factsheet is not meant to provide legal advice. Consult your lawyer
if you have questions about your legal obligations.
For more information on the NMA, call the Nutrient Management Information
Line at 1-866-242-4460, e-mail nman.omafra@ontario.ca
or visit the OMAFRA website.
Factsheets are continually being updated so please ensure that you have
the most recent version.
Related Links
For more information:
Toll Free: 1-877-424-1300
Local: (519) 826-4047
E-mail: ag.info.omafra@ontario.ca
|