|
|
Constructing
an Earthen Liquid Nutrient or Runoff Storage Facility
 |
| Agdex#: |
720/538 |
| Publication Date: |
01/06 |
| Order#: |
06-005 |
| Last Reviewed: |
01/06 |
| History: |
|
| Written by: |
Don Hilborn - Engineer/OMAFRA;
John Johnson - Engineer/OMAFRA |
Table of Contents
- Introduction
- Scope
- Key Points
- Sizing
- Siting
- Setbacks Not Specified in the NMA Regulation
- Professional Involvement
- Specific Criteria Required by the NMA Regulation
- Appendix A: Site Characterization/Investigation Criteria
Specified in the Regulation
- Appendix B: Engineer Commitment Certificate - Form
A
- Related Links
Introduction
The following document provides recommendations to address the construction
of an earthen liquid nutrient storage or runoff storage facility as
required by the Nutrient Management Act, 2002, (NMA) and the associated
Regulation O. Reg. 267/03 (as amended to O. Reg. 511/05). Figure
1 shows a lined, earthen storage facility.
Figure 1. This earthen storage facility has
been equipped with a secondary containment liner to provide additional
protection for surface and ground water.

| Top of Page |
Scope
This Factsheet applies to a permanent earthen storage facility having
either:
- 14 or more days of storage capacity (for the associated facility)
or
- a maximum depth of liquid nutrients of 100 mm (4 in.) or more.
Key Points
- Earthen nutrient storage facilities without any incorporated concrete
structure(s) are typically not deemed to be a structure in Ontario
and consequently do not require a building permit; however the Nutrient
Management Act regulates their siting and construction.
- At least 2 levels of underground protection are required for these
storage facilities.
- The above ground portion must have secondary containment or appropriate
landscape features.
- Most of the design must be carried out under the supervision of
a professional engineer. Some aspects of the design may involve a
professional geoscientist.
- Proper setbacks from sensitive features such as wells, surface
water and conflicting uses must be met.
- Any perforated tile drain close to the storage must be removed
unless it is required for a foundation drain.
- If any component of the facility is constructed of concrete, that
component must be designed and constructed using the concrete and
steel storage specifications (see OMAFRA Factsheet 06-001, Constructing
a Permanent Concrete or Steel Liquid and Runoff Storage Facility
or other applicable standards). This may trigger the need for a building
permit.
| Top of Page |
Sizing
For a regulated farm the minimum capacity of the storage must:
- include precipitation directly entering an open-top storage of
2.27 mm/day (example: if the storage is designed for 240 days of capacity,
the precipitation input should be 2.27 x 240 days or 0.55 m over
the surface area of the storage)
- include a freeboard1
of 0.30 m
- include 240 days of manure and bedding production2
from attached livestock facilities with the following exceptions:
- where the farmer sends some of the manure to a broker and the
aggregate storage capacity of the broker and the farmer is 240
days (e.g. a layer chicken operation has an agreement with a broker
who can provide 60 days of storage. The manure storage at the
layer chicken operation would only need to be designed for 180
days)
- where the period of use of the barn is less than 240 days
(e.g. a beef feeder operation houses the animals for 180 days
in the barn from Nov. 1 until they go to pasture on May 1.
The manure storage would only need to be designed for 180 days)
- where the farmer's nutrient management plan permits lesser
periods of storage, (e.g. a NMP demonstrates that manure can be
applied at a frequency that is less than 240 days). NOTE: for
liquid manure storage this can only be used if the number of farm
animals on the farm unit has not increased since Sept. 30, 2003
or
- where the farmer's nutrient management strategy permits lesser
periods of storage via the use of transfers out of the farm unit
(e.g. a dairy farm transfers its manure off-site every three months
to another farm unit. The manure storage at the dairy farm would
only have to be designed for 3 months).
1 Freeboard is an additional depth
of storage required to deal with wave action due to wind or agitation
and to provide a safety factor to address unexpected circumstances (e.g.
excessive rainfall, leaks in water system, etc.). It is added to the
calculated depth required for manure production and precipitation.
2 The manure and bedding production
must be based on numbers shown in Table 3.1 of the Nutrient Management
Protocol (note MSTOR, a computer program developed by OMAFRA will include
these numbers and can be used to complete the calculations.)
| Top of Page |
Siting
The following distances (from the top of the inside sloping face of
the storage) must be met:
- Well setback - the NMA Regulation requires that any new
or expanding storage be at least:
- 15 m from a drilled well that has a depth of at least 15 m
and a watertight casing that extends to a depth of at least 6
m below ground level
- 100 m from a municipal well and
- 30 m from any other well.
- Flow path requirement - the NMA Regulation specifies that
a farm constructing or expanding any nutrient or runoff storage, must
be at least 50 m away from surface water or a tile inlet or have a
flow path that is at least 50 m (165 ft.) long. The flow path is the
distance over ground any liquids would have to flow from the storage
before entering surface water or a tile inlet. This flow path does
not always follow a straight line as illustrated in Figure
2.
Figure 2. A flow path does not always follow
a straight line. This required flow path is used to provide opportunities
for flow control in the event of a spill.

- 1 in 100 Flood Line- The NMA Regulation requires the storage
to be constructed above any one in 100 year flood line established
by a municipality or conservation authority (if the municipality or
conservation authority has established such flood lines) unless a
permit for the storage is issued under Section 28 of the Conservation
Authorities Act.
- Tile drains (field) - All perforated drains within 15 m
(50 ft.) must be located, intercepted and removed. Any flow from a
field drainage system or piped municipal drain must be redirected
away from the storage.
- Tile drains (structural) - The following two options can
be used to manage water from a perforated foundation drain within
15 m of a manure storage facility:
- any perimeter drain for the storage must run through an observation
and shutoff station prior to entering another drainage system
or surface water. This special catch basin has 2 purposes. It
can be used to detect leakage from the storage to the foundation
drains. In addition, it is used to shut off the flow and allow
steps to be taken to identify and deal with the leakage. Figure
3 shows a typical observation and shutoff station used to
provide access to the tile drain.
- collect the foundation drain water and discharge it to a treatment
system.
Figure 3. An observation and shutoff station
is used to provide access to a perimeter drain if required. Possible
contaminated flow can be observed and blocked. Steps can then be taken
to address the situation.

| Top of Page |
Setbacks Not Specified in the NMA Regulation
Minimum Distance Separation (MDS II) Formula
- MDS II determines minimum separation distances between proposed
new, enlarged or remodeled livestock facilities and/or permanent manure
storages and other existing or approved development (e.g. neighbouring
houses, areas zoned residential, lot lines, road allowance, etc.)
- MDS II is triggered when a building permit is required, but because
earthen storages are not considered to be a building, they do not
require a building permit. However, this does not exclude them
from the requirement for siting according to the MDS formula. Best
Management Practices recommend the MDS formula be followed in all
cases and this is backed up by the Provincial Policy Statement, 2005,
policy number 1.1.4.1 (c):
- 'New land uses, including the creation of lots, and new or expanding
livestock facilities shall comply with the minimum distance separation
formulae.'
- The term livestock facility is defined in the new MDS-2005 as:
- 'Permanent structures with livestock-occupied portions, intended
for the keeping or housing of livestock, including feedlots, and
containing one or more barns or structures, Includes manure storages,
whether associated with a livestock facility or not….'
- For more information, contact your Nutrient Management Consultant
or local OMAFRA engineer.
Other Municipal Setbacks
- Contact your municipality for more information on other required
setbacks
| Top of Page |
Professional Involvement
For the construction or expansion of a permanent liquid nutrient storage
facility [O. Reg. 267/03 [as amended to O. Reg. 511/05]] requires that
professionals complete the following:
- Design - a professional engineer must complete the design,
including any monitoring system (if installed).
- Site investigation - a professional engineer or a professional
geoscientist must carry out a site characterization assessment.
- Supervision - the construction or expansion must take place
under the supervision of a professional engineer. This supervision
process has been shown to be very important in the construction of
a liquid manure or nutrient storage system.
- Commitment certificate - the engineer must sign the Engineer's
Commitment Certificate (see Appendix B) prior to the construction.
The farmer must submit this with the Nutrient Management Strategy.
- Additional requirements - other municipal and provincial
requirements may need to be addressed on a site-specific basis. For
more information, contact your local building official.
| Top of Page |
Specific Criteria Required by the NMA Regulation
- General design - the facility, including any associated
plumbing systems used to transfer manure or liquid nutrients, must
be "designed to minimize leakage, minimize corrosion and to be structurally
safe and sound." [O.Reg. 267/03 as amended: sentence 71. (1)(b)]
- Site requirements - There are two options for earthen, liquid
nutrient storage facilities:
- Option 1 - Storage for liquid agricultural source materials
(excluding manure): Must satisfy the criteria as specified
in Figure 4. The Regulation specifies details
regarding interior surface treatment, soil anomalies and above-ground
berm construction. For example, the soils that form the inner
surface must be disked to a depth of 150 mm and recompacted to
meet a hydraulic conductivity of no more than 1 x 10-8 m/sec.
- Option 2 - Storage for liquid agricultural source materials
(including manure): Must satisfy the criteria as specified
in Figure 5. In addition to the 2 m of hydraulically
secure soil, this option requires the installation of a compacted
soil, geo-synthetic or synthetic liner. Liner installation details
are specified in the NMA Regulation. For example, the Regulation
specifies that:
- liners must be continuous under the storage facility and
must extend to a level equal to the surrounding ground surface,
unless the designer specifies otherwise.
Figure 4. Design criteria for smaller runoff
storage facilities, storing liquid agricultural source materials other
than manure.

Figure 5. Design criteria for storage facilities,
storing liquid nutrients and/or manure.
- Compacted soil liner - if this type of liner is used it must
be constructed:
- using a minimum of 6 layers, of 150 mm thick material on the
inside sloping surfaces
- using a minimum of 4 layers of 150 mm thick material on the
floor surface.
- Hydraulic conductivity - it is recommended that a liner
should have a hydraulic conductivity of no more than 1 x 10-9
m/sec.
- Site investigation - is required for all permanent, liquid
nutrient storage facilities. (See Appendix A)
- Secondary containment - If the liquid level in the storage
facility is partially or wholly above the surface of the surrounding
soil, the following options apply:
- a professional engineer can determine that the storage and
landscape features around the facility are adequate to ensure
that a secondary containment system is not required; or
- the designer incorporates a secondary containment system, with
a capacity of 110% of the above ground portion of the volume of
material stored.
- Transfer systems - all connections in a liquid transfer system
must be installed using specifically designed fittings and gaskets
that are compatible with the pipe material
- all pipes entering a liquid manure facility must have a flexible,
watertight gasket or membrane installed between the pipe and the
floor or wall of the storage structure to serve as an anti-seepage
collar
- any transfer system having an opportunity to backflow to the
pump or pump-out chamber must have both a primary and secondary
shutoff valve.
- Floor transfer systems - must be constructed of concrete
and be capable of containing and transferring liquid to a storage
facility. A floor transfer system does not include:
- areas within the barn, designed to house livestock, but not
intended to collect liquid manure
- areas under dairy free-stalls
- feed trough areas
- floors under manure pack areas.
- Ventilation - All covered storage systems must have a ventilation
system that may be either a powered or natural ventilation system
to prevent the accumulation of corrosive or noxious gases.
- Alternative design - An engineer can produce a design that
is equivalent to or makes use of materials that are equivalent to
those referred to in the Act or Regulation.
| Top of Page |
Appendix A: Site Characterization/Investigation Criteria
Specified in the Regulation
Site characterization is a process followed for all new, permanent
liquid manure storage structures to determine how much protection is
provided by the natural environment on the proposed building site. A
basic site characterization evaluation considers the soil type and water
table location, etc. In cases where the natural site does not provide
sufficient protection, it may be necessary to use a synthetic liner,
a geo-synthetic liner or an engineered soil (usually clay) liner to
enhance the protection for surface and/or ground water.
You must hire a professional engineer or professional geoscientist
to make the site assessment. OMAFRA can provide a partial listing of
engineering and geotechnical companies who are familiar with agricultural
projects. These individuals will take soil samples and investigate the
location of permanent and naturally or artificially occurring water
tables. These tests can be carried out using a boring machine or a backhoe/excavator.
The machine must be capable of boring or excavating to a minimum depth
of 1.5 m below the lowest excavation for the structure. If an earthen
floor is desired, the depth of investigation must be 2.5 m below the
lowest excavation for the structure. One borehole or excavation is required
per 1,000 m2 of ground floor area for the facility being
constructed. The engineer or geoscientist may require more samples to
be taken, due to site conditions.
The soil samples must be evaluated by a geotechnical laboratory to
determine their physical properties. The geotechnical evaluation will
determine if the soil provides a level of protection equivalent to OMAFRA's
guidelines. These guidelines are listed below:
- The saturated hydraulic conductivity of the soil is a measure of
how rapidly water (and nutrients) can move through the soil. For protection
of the environment, slower is better. Hydraulically secure soil has
a maximum saturated hydraulic conductivity of 1 x 10-8
m/sec. An indication of the saturated hydraulic conductivity of the
soil can be obtained by several means:
A professional geoscientist may alternatively provide data or a design
that will provide a level protection that is an equivalent to the above
alternatives.
An important part of a site characterization study is to determine
the level of the water tables in the vicinity of the proposed liquid
nutrient storage facility. There can be several water table levels on
a building site. Some of these occur naturally, while others may have
been caused by other construction projects. Constructing any part of
a storage facility below a water table is not advised. In some cases,
a water table can be artificially lowered by providing a drainage system
surrounding the storage. This drainage system would require a monitoring
catch basin to show that no direct contamination is occurring.
In some problem soils, the best alternative may be to make use of a
synthetic, geosynthetic or engineered soil liner to provide secondary
containment. With two levels of protection for the environment, the
protection offered by the proposed building site becomes less critical.
| Top of Page |
Appendix B - Engineer Commitment Certificate
- Form A
Project: ______________________________________________________________________________
Name / Location
This is to Certify that I:
|
________________________
Owner
|
___________________
Signature
|
_______________
Date
|
understand that under the Nutrient Management Act, 2002, I am required
to retain engineering services for specific projects and situations.
Therefore I have retained the following Professional Engineer:
|
________________________
Engineers name
|
___________________
Signature
|
_______________
Date
|
to undertake the overall coordination and completion of the engineering
design and general review of construction; or
I have retained the following Professional Engineers to provide engineering
services for the following components of the engineering design and
review of construction:
| Design Component |
Engineers Name |
Engineers Signature |
Address |
Phone |
| Site Characterization * - sub-surface information, soil properties,
water table and bedrock location (if critical) |
|
|
|
|
| Liquid Storage Facilities drawings and design details for
liquid storage construction |
|
|
|
|
| Solid Storage Facilities drawings and design details for
solid storage construction if applicable |
|
|
|
|
| Earthen Storage Facilities drawings and design details
for earthen storage construction |
|
|
|
|
| Synthetic or Natural Liner design details, including details
of inspection and testing of seams. |
|
|
|
|
| Transfer Systems drawings and design details for connections,
materials, etc. |
|
|
|
|
Do you know about Ontario's new Nutrient Management Act?
The provincial Nutrient Management Act (NMA) and the Regulation 267/03
regulates the storage, handling and application of nutrients that could
be applied to agricultural crop land. The objective is to protect Ontario's
surface and groundwater resources.
Please consult the regulation and protocols for the specific legal
details. This Factsheet is not meant to provide legal advice. Consult
your lawyer if you have questions about your legal obligations.
For more information on the NMA, call the Nutrient Management Information
Line at 1-866-242-4460, e-mail nman.omafra@ontario.ca
or visit the OMAFRA website.
Factsheets are continually being updated so please ensure that you
have the most recent version.
This Factsheet was reviewed by the following OMAFRA Engineers: Harold
Cuthbertson, P.Eng., Brighton; Hugh Fraser, P.Eng., Vineland
Station; Harold House, P.Eng., Clinton; Kevin McKague,
P.Eng., Woodstock; and Robert Stone, P.Eng., Brighton.
Related Links
| Top of Page |
For more information:
Toll Free: 1-877-424-1300
Local: (519) 826-4047
E-mail: ag.info.omafra@ontario.ca
|