Constructing a Permanent Concrete
or Steel Liquid Nutrient or Runoff Storage Facility
We are updating this page to reflect current regulations.
Information on this page about regulations under the Nutrient Management
Act, 2002 and the Environmental Protection Act is out of
date. On September 18, 2009 new regulations affecting those applying non-agricultural
source materials on agricultural lands were filed. Please visit www.ontario.ca/nasm-omafra
for more information.
Table of Contents
- Introduction
- Scope
- Key Points
- Sizing
- Siting
- Setbacks Not Specified in the NMA Regulation
- Professional Involvement
- Specific Criteria Required by the NMA Regulation
- Appendix A: Site Characterization/Investigation Criteria
Specified in the Regulation
- Appendix B: Engineer Commitment Certificate - Form A
- Related Links
Introduction
The following document provides recommendations to address the construction
of liquid nutrient storage or runoff storage structures as required by
the Nutrient Management Act, 2002 (NMA) and the associated Regulation
O. Reg. 267/03 (as amended to O. Reg. 511/05). Figure
1 illustrates the type of structure described in this Factsheet.

Figure 1. Open,
circular, liquid tanks are commonly used on farms to store manure from
livestock operations.
Scope
This Factsheet applies to a permanent storage facility constructed using
steel, concrete or equivalent material having either:
- 14 or more days of storage capacity (for the associated facility)
or
- a maximum depth of liquid nutrients of 100 mm (4 in.) or more.
Key Points
- A building permit is required for the construction of all permanent
(non earthen) liquid nutrient (including manure) storage structures.
- At least 2 levels of underground protection are required for these
storages.
- The above ground portion must have secondary containment or additional
strength or appropriate landscape features.
- Most of the design must be carried out under the supervision of a
professional engineer. Some aspects of the design may involve a professional
geoscientist.
- Proper setbacks from sensitive features such as wells, surface water
and conflicting uses must be met.
- Any perforated tile drain close to the storage must be removed unless
it is required as a foundation drain.
- If any component of the facility is constructed of earth, that component
must be designed and constructed using the specifications for earthen
storage construction (see OMAFRA Factsheet Order No. 06-005, Constructing
a Permanent Earthen Liquid Nutrient or Runoff Storage Facility or
other applicable standards).
Sizing
For a regulated farm the minimum capacity of the storage must:
- include 240 days of manure and bedding production1
from associated livestock facilities with the following exceptions:
- if the farmer sends some of the manure to a broker and the aggregate
storage capacity of the broker and the farmer is 240 days (e.g.
a layer chicken operation has an agreement with a broker who can
provide 60 days of storage. The manure storage at the layer chicken
operation would only have to be designed for 180 days)
- if the period of use of the barn is less than 240 days (e.g.
a beef feeder operation houses the animals for 180 days from Nov.
1 until they go to pasture on May 1. The manure storage would only
have to be designed for 180 days)
- if the farmers nutrient management plan permits lesser
periods of storage, (e.g. a NMP demonstrates that manure can be
applied at a frequency that is less than 240 days). NOTE: for liquid
manure storage this can only be used if the number of farm animals
on the farm unit has not increased since Sept. 30, 2003; or
- if the farmers nutrient management strategy permits lesser
periods of storage via the use of transfers out of the farm unit
(e.g. a dairy farm transfers its manure off-site every 3 months
to another farm unit. The manure storage at the dairy farm would
only have to be designed for 3 months).
- include precipitation directly entering an open top storage of 2.27
mm/day (example: if the storage is designed for 240 days of storage,
the precipitation input should be 2.27 x 240 days or 0.55 m (metres)
over the surface area of the storage).
- include freeboard2
of 0.3 m.
- The manure and bedding production must
be based on numbers shown in Table 3.1 of the Nutrient Management Protocol
(note MSTOR a computer program developed by OMAFRA will include these
numbers and can be used to complete the calculations.)
- Freeboard is an additional depth of storage
required to deal with wave action due to wind, agitation and to provide
a safety factor to address unexpected circumstances (for example, excessive
rainfall, leaks in water system, etc.). It is added to the calculated
depth required for manure production and precipitation.
Siting
All of the following criteria must be met:
- Well setback The NMA Regulation requires that any new or expanding
storage be at least:
- 15 m from a drilled well that has a depth of at least 15 m and
a watertight casing that extends to a depth of at least 6 m below
ground level
- 100 m from a municipal well and
- 30 m from any other well.
- Flow path requirement the NMA Regulation specifies that a
farm, constructing or expanding a nutrient storage must be at least
50 m away from surface water or a tile inlet or have a flow path that
is at least 50 m (165 ft) long. The flow path is the distance over ground
any liquids would have to flow from the storage before entering surface
water or a tile inlet. This flow path does not necessarily follow a
straight line as illustrated by Figure 2.

Figure 2. A flow path does not always follow a straight
line. This required flow path is used to provide opportunities for flow
control in the event of a spill.
- 1 in 100 Flood Line The NMA Regulation requires the storage
to be constructed outside of any one in 100 year flood line that has
been established by a municipality or Conservation Authority (if the
municipality or Conservation Authority has established such flood lines),
unless a permit for the storage is issued under Section 28 of the Conservation
Authorities Act.
- Tile drains (field) All perforated drains within 15 m
(50 ft) must be located, intercepted and removed. Any flow from a field
drainage system or piped municipal drain must be redirected away from
the storage.
- Tile drains (structural) The following 2 options can be used
to manage water from a perforated foundation drain within 15 m of a
manure storage facility:
- Any perimeter drain for the storage must run through an observation
and shutoff station prior to entering another drainage system or
surface water. This special catch basin has 2 purposes. It can be
used to detect leakage from the storage to the foundation drains.
In addition, it is used to shut off the flow and allow steps to
be taken to identify and deal with the leakage. Figure
3 shows a typical observation and shutoff station used to provide
access to the tile drain.
- Collect the foundation drain water and discharge it to a treatment
system.
Setbacks Not Specified in the NMA Regulation
Minimum Distance Separation (MDS II) Formula:
- MDS II determines minimum separation distances between proposed new,
enlarged or remodeled livestock facilities and/or permanent manure storages
and other existing or approved development (e.g. neighbouring houses,
areas zoned residential, lot lines, road allowance, etc.).
- MDS II is triggered when a building permit is required. In addition,
Best Management Practices recommend the MDS formula be followed in all
cases and this is backed up by the Provincial Policy Statement, 2005,
policy number 1.1.4.1 (c):
- New land uses, including the creation of lots, and new or
expanding livestock facilities shall comply with the minimum distance
separation formulae
- The term livestock facility is defined in the new MDS-2005 as
- Permanent structures with livestock-occupied portions, intended
for the keeping or housing of livestock, including feedlots, and containing
one or more barns or structures, Includes manure storages, whether associated
with a livestock facility or not
.
- For more information, contact your Nutrient Management Consultant
or local OMAFRA engineer.
Other Municipal Setbacks
- Contact your municipality for more information on other required setbacks.

Figure 3.An observation and shutoff station is used to
provide access to a perimeter drain if required. Possible contaminated
flow can be observed and blocked. Steps can then be taken to address the
situation.
Professional Involvement
For the construction or expansion of a permanent liquid nutrient storage
structure, O. Reg. 267/03 (as amended to O. Reg. 511/05) requires that
professionals complete the following:
- Design a professional engineer must design the construction
or expansion, including any monitoring system
- Site investigation a professional engineer or a professional
geoscientist must carry out a site characterization assessment.
- Supervision the construction or expansion must take place under
the supervision of a professional engineer. This supervision process
has been shown to be very important in the construction of a liquid
manure or nutrient storage system.
- Commitment certificate the engineer must sign the Engineers
Commitment Certificate (see Appendix B) prior to the
construction. The farmer must submit this with the Nutrient Management
Strategy.
- Additional requirements there are other municipal or provincial
requirements including:
- For a permanent liquid nutrient storage structure, the building
permit process requires that an engineer provide a design for the
structure, meeting the requirements of the Ontario Building Code
and the National Farm Building Code for Canada.
Specific Criteria Required by the NMA Regulation
- General design the facility, including any associated plumbing
systems used to transfer manure or liquid nutrients, must be designed
to minimize leakage, minimize corrosion and to be structurally safe
and sound. [O.Reg. 267/03, as amended: sentence 71. (1)(b)]
- Structural systems Figure 4 shows the available
structural systems and surrounding soil conditions that are deemed to
provide 2 layers of protection.
- Concrete floors concrete floors must be a minimum of 125 mm
thick unless a professional engineer specifies otherwise.
- Structural calculations a designer is required to apply an
importance factor of 1.0 to a permanent liquid nutrient storage facility.
An importance factor of 0.8 is commonly applied by an engineer in the
design of other farm structures of low human occupancy.
- Type of concrete if used, concrete must be strong and durable
enough to resist the environmental conditions and must protect the reinforcing
steel (if used) from potentially corrosive environments.
- Site investigation a site charterization/ investigation is
required for all permanent, liquid manure or nutrient storage facilities.
(See Appendix A)
- Secondary containment if the liquid level in the storage facility
is partially or wholly above the surface of the surrounding soil, the
following options apply:
- an engineer can apply a load factor of 1.5 or another value that
they specify. This increases the overall factor of safety for the
structure ;or
- a professional engineer can determine that the storage and landscape
features around the facility are adequate to ensure that a secondary
containment system is not required; or
- the designer incorporates a secondary containment system, with
a capacity of 110% of the above ground portion of the volume of
material stored.
- Liners some site conditions require that an engineer use synthetic,
geosynthetic or compacted soil liners. Liner installation details are
specified in the NMA Regulation. For example, the NMA Regulation indicates
that the liner must be continuous under the floor and footings of the
facility and must extend up the wall to the level of the top of the
ground surface. Alternative materials can be used if the engineer specifies
and supervises their use.
- Transfer systems all connections in a liquid transfer system
must be installed using specifically designed fittings and gaskets that
are compatible with the pipe material.
- All pipes entering a liquid manure facility must have a flexible,
watertight gasket or membrane installed between the pipe and the
floor or wall of the storage structure to serve as an anti-seepage
collar.
- Any transfer system having an opportunity to backflow to the pump
or pump-out chamber must have both a primary and secondary shutoff
valve.
- Floor transfer systems must be constructed of concrete and be
capable of containing and transferring liquid to a storage facility.
A floor transfer system does not include:
- areas within the barn, designed to house livestock, but not
intended to collect liquid manure
- areas under dairy free-stalls
- feed trough areas
- floors under manure pack areas.
- Ventilation All covered storage systems must have a ventilation
system that may be either a powered system or a natural system to prevent
the accumulation of corrosive or noxious gases.
- Alternative design an engineer can produce a design that is
equivalent to or makes use of materials that are equivalent to those
referred to in the Act or Regulation.
Figure 4. Provides a summary of the alternative structural
systems that can be used, depending on conditions at the building site.
A site characterization report will determine how much natural security
the site provides for groundwater sources.
Appendix A: Site Characterization/Investigation Criteria
Specified in the Regulation
Site characterization is a process followed for all new, permanent liquid
manure storage structures to determine how much protection is provided
by the natural environment on the proposed building site. A basic site
characterization evaluation considers the soil type and water table location,
etc. In cases where the natural site does not provide sufficient protection,
it may be necessary to use a synthetic liner, a geo-synthetic liner or
an engineered soil (usually clay) liner to enhance the protection for
surface and/or ground water.
You must hire a professional engineer or professional geoscientist to
make the site assessment. OMAFRA can provide a partial listing of engineering
and geotechnical companies familiar with agricultural projects. These
individuals take soil samples and investigate the location of permanent
and naturally or artificially occurring water tables. These tests can
be carried out using a boring machine or a backhoe/excavator. The machine
must be capable of boring or excavating to a minimum depth of 1.5 m below
the lowest excavation for the structure. If an earthen floor is desired,
the depth of investigation must be 2.5 m below the lowest excavation for
the structure. One borehole or excavation is required per 1,000 m2
of ground floor area for the facility being constructed. The engineer
or geoscientist may require more samples to be taken, due to site conditions.
The soil samples must be evaluated by a geotechnical laboratory to determine
their physical properties. The geotechnical evaluation will determine
if the soil provides a level of protection equivalent to OMAFRAs
guidelines. These guidelines are listed below:
- The saturated hydraulic conductivity of the soil is a measure of how
rapidly water (and nutrients) can move through the soil. For protection
of the environment, slower is better. Hydraulically secure soil has
a maximum saturated hydraulic conductivity of 1 x 10-8 m/sec.
An indication of the saturated hydraulic conductivity of the soil can
be obtained by several means:
A professional geoscientist may alternatively provide data or a design
that will provide a level of protection that is an equivalent to the above
alternatives.
An important part of a site characterization study is to determine the
level of the water tables in the vicinity of the proposed liquid nutrient
storage facility. There can be several water table levels on a building
site. Some of these occur naturally, while others may have been caused
by other construction projects. Constructing any part of a storage facility
below a water table is not advised. In some cases, a water table can be
artificially lowered by providing a drainage system surrounding the storage.
This drainage system would require a monitoring catch basin to show that
no direct contamination is occurring.
In some problem soils, the best alternative may be to make use of a synthetic,
geosynthetic or engineered soil liner to provide secondary containment.
With two levels of protection for the environment, the protection offered
by the proposed building site becomes less critical.
Appendix B - Engineer Commitment Certificate
Form A
Project (Name/Location):
______________________________________________________________
This is to Certify that I:
______________________________________________________________
Owner
______________________________________________________________
Signature
______________________________________________________________
Date
understand that under the Nutrient Management Act, 2002, I am required
to retain engineering services for specific projects and situations. Therefore
I have retained the following Professional Engineer:
______________________________________________________________
Engineers name
______________________________________________________________
Signature
______________________________________________________________
Date
to undertake the overall coordination and completion of the engineering
design and general review of construction; or
I have retained the following Professional Engineers to provide engineering
services for the following components of the engineering design and review
of construction:
| Design Component |
Engineers Name |
Engineers Signature |
Address |
Phone |
| Site Characterization * - sub-surface information, soil properties,
water table and bedrock location (if critical) |
|
|
|
|
| Liquid Storage Facilities drawings and design details for
liquid storage construction |
|
|
|
|
| Solid Storage Facilities drawings and design details for
solid storage construction if applicable |
|
|
|
|
| Earthen Storage Facilities drawings and design details for
earthen storage construction |
|
|
|
|
| Synthetic or Natural Liner design details, including details
of inspection and testing of seams. |
|
|
|
|
| Transfer Systems drawings and design details for connections,
materials, etc. |
|
|
|
|
Do you know about Ontario's Nutrient Management Act?
The provincial Nutrient Management Act (NMA) and the Regulation 267/03
regulates the storage, handling and application of nutrients that could
be applied to agricultural crop land. The objective is to protect Ontario's
surface and groundwater resources.
Please consult the regulation and protocols for the specific legal details.
This Factsheet is not meant to provide legal advice. Consult your lawyer
if you have questions about your legal obligations.
For more information on the NMA, call the Nutrient Management Information
Line at 1-866-242-4460, e-mail nman.omafra@ontario.ca
or visit the OMAFRA website.
Factsheets are continually being updated so please ensure that you have
the most recent version.
Related Links
For more information:
Toll Free: 1-877-424-1300
Local: (519) 826-4047
E-mail: ag.info.omafra@ontario.ca
|